Task #1478
Settlement Process email notification - Global Trade
Status: | Work Completed-End life cycle | Start date: | May 07, 2012 | |
---|---|---|---|---|
Priority: | Normal | Due date: | May 09, 2012 | |
Assignee: | Hosseiny Elham | % Done: | 100% | |
Category: | - | Spent time: | - | |
Target version: | - |
Description
Settlement process email for Global Trade.
- Trade Entry - Single Trade and Trade Upload
Send email to Checker
- Trade Verification
Send email to Checker
- Trade Authorization
Send email to MBB Custody Team
History
#1 Updated by Zayani Zakaria over 12 years ago
- Status changed from New - Begin Life Cycle to Development / Work In Progress
- % Done changed from 0 to 60
#2 Updated by Zayani Zakaria over 12 years ago
- % Done changed from 60 to 80
#3 Updated by Zayani Zakaria over 12 years ago
- Status changed from Development / Work In Progress to Internal Testing
- Assignee changed from Zayani Zakaria to Hosseiny Elham
- % Done changed from 80 to 0
#4 Updated by Hosseiny Elham over 12 years ago
- Status changed from Internal Testing to Pending SIT Deployment
- % Done changed from 0 to 80
tasted was ok.
#6 Updated by Hosseiny Elham about 12 years ago
- Status changed from Pending SIT Deployment to Work Completed-End life cycle