Bug #197
Need to Change the Total to Estimated Total in Printing Format.
Status: | Closed - End of life cycle | Start date: | June 30, 2010 | |
---|---|---|---|---|
Priority: | Normal | Due date: | July 01, 2010 | |
Assignee: | Nor Shuhaida Subri | % Done: | 100% | |
Category: | - | Spent time: | - | |
Target version: | - |
Description
Need to Change the Total to Estimated Total in Printing Format.
Actual Format = Total
Expected Format = Estimated Total
History
#1 Updated by Nandong Frank about 14 years ago
- Due date set to July 01, 2010
#2 Updated by Tan Lee Yong about 14 years ago
Need status update
#3 Updated by Nor Shuhaida Subri about 14 years ago
- Status changed from New - Begin Life Cycle to Work Completed-End life cycle
- % Done changed from 0 to 100
Update Total to Estimated Total inside Resource Properties file
#4 Updated by Tan Lee Yong about 14 years ago
- Status changed from Work Completed-End life cycle to Closed - End of life cycle