Task #251

UAT Monitoring for Bill Payment Enhancement

Added by Tan Lee Yong about 14 years ago. Updated almost 14 years ago.

Status:Closed - End of life cycleStart date:July 19, 2010
Priority:NormalDue date:September 24, 2010
Assignee:Low Jelson% Done:

100%

Category:-Spent time:-
Target version:-

Description

Monitor the UAT progress for the Bill Payment Enhancement project. Close this when obtained the UAT sign off.

History

#1 Updated by Tan Lee Yong about 14 years ago

  • Due date changed from July 16, 2010 to August 06, 2011
  • Start date changed from July 07, 2010 to July 19, 2010

Monitor Internal and External UAT progress.
Internal UAT 19/7 - 30/7
External UAT 2/8 - 6/8

#2 Updated by Tan Lee Yong about 14 years ago

Any update on this? When is the targeted UAT sign off date?

#3 Updated by Low Jelson about 14 years ago

  • Status changed from New - Begin Life Cycle to Development / Work In Progress
  • % Done changed from 0 to 90

UAT completed for Bill Payment Enhancement. Pending for UAT sign off. Vincent will prepare migration plan for coming migration next week.

#4 Updated by Tan Lee Yong almost 14 years ago

  • Due date changed from August 06, 2011 to September 24, 2010
  • Status changed from Development / Work In Progress to Work Completed-End life cycle
  • % Done changed from 90 to 100

Migrated to production on 20/09/2010

#5 Updated by Low Jelson almost 14 years ago

  • Status changed from Work Completed-End life cycle to Closed - End of life cycle

CR delivered