Task #3121
M2U: Project Plan
Status: | Work Completed-End life cycle | Start date: | July 03, 2013 | |
---|---|---|---|---|
Priority: | Normal | Due date: | July 27, 2013 | |
Assignee: | - | % Done: | 0% | |
Category: | - | Spent time: | 5.00 hours | |
Target version: | - |
Description
Project plan creation and finalization with customer
History
#1 Updated by Tan Lee Yong about 11 years ago
- Status changed from New - Begin Life Cycle to Development / Work In Progress
I have done the first draft of the project plan and submitted to customer on July 2nd 2013
#2 Updated by Tan Lee Yong over 10 years ago
- Status changed from Development / Work In Progress to Work Completed-End life cycle