Change #3205
Authorization - Approval
Status: | Work Completed-End life cycle | Start date: | July 09, 2013 | |
---|---|---|---|---|
Priority: | Normal | Due date: | ||
Assignee: | Hosseiny Elham | % Done: | 0% | |
Category: | IBAM - Authorization | Spent time: | - | |
Target version: | - |
Description
Anwar,
Kindly assist to change these .
Step one to re - produce:- 1. click on IBAM.
- 2. Click on Approval
- 3. Select IBAM Authorization.
- remove long descroption. As we discussed together.*
History
#1 Updated by Norhaidah Md Dasuki about 11 years ago
- Project changed from IBAM to 1.IBAM
- Category set to IBAM - Authorization
#2 Updated by Hosseiny Elham about 11 years ago
- Assignee changed from Syahrul Anwar to Anwar Khairul
#3 Updated by Anwar Khairul about 11 years ago
- Status changed from New - Begin Life Cycle to Finished Development
- % Done changed from 0 to 100
Removed. Completed.
#4 Updated by Anwar Khairul about 11 years ago
- Status changed from Finished Development to Internal Testing
- Assignee changed from Anwar Khairul to Hosseiny Elham
- % Done changed from 100 to 0
#5 Updated by Hosseiny Elham about 11 years ago
- Status changed from Internal Testing to Work Completed-End life cycle
Fixed and retested succesfully