Check box is automatically ticked from previous session.
Step to reproduce
Step 1- Delete 3rd Party Beneficiary Acc Maintenance
- Add 3rd Party Beneficiary Acc Maintenance
- After add, see the 3rd Party Beneficiary Acc Maintenance List, check box have been automatically ticked from previous session.
History
#1 Updated by Anwar Khairul about 11 years ago
- Status changed from New - Begin Life Cycle to Finished Development
- % Done changed from 0 to 100
Root cause: no reset bean during main action
Solution: add reset bean function
#2 Updated by Anwar Khairul about 11 years ago
- Status changed from Finished Development to Internal Testing
- Assignee changed from Anwar Khairul to Siti Norahayu Mohd Desa
#3 Updated by Siti Norahayu Mohd Desa about 11 years ago
- Status changed from Internal Testing to Work Completed-End life cycle
Tested & Passed. TQ