BIB : Print Receipt - New 3rd Party and Favourite 3rd Party Transfer
Status: | Closed - End of life cycle | Start date: | July 22, 2013 | |
---|---|---|---|---|
Priority: | Normal | Due date: | July 22, 2013 | |
Assignee: | Norhaidah Md Dasuki | % Done: | 100% | |
Category: | - | Estimated time: | 2.00 hours | |
Target version: | - | Spent time: | 9.00 hours |
Description
Salam Syahrul,
As per explanation before,kindly assist on the issue.
- Please rearrange the sequence of the receipt details as the result page (Refer attachment)
- Added remarks on the email format details
History
#1 Updated by Lizahwati Basirun about 11 years ago
Hi Syahrul,
For the Beneficiary Email, no need to add into the Receipt.Thank you.
#2 Updated by Syahrul Anwar about 11 years ago
- Status changed from New - Begin Life Cycle to Finished Development
- % Done changed from 0 to 100
- Estimated time set to 2.00
1) Please rearrange the sequence of the receipt details as the result page (Refer attachment) -done
solution add email in print receipt map
2) Added remarks on the email format details -done
solution add remarks in email method
#3 Updated by Lizahwati Basirun about 11 years ago
- Status changed from Finished Development to Development / Work In Progress
- % Done changed from 100 to 80
Hi Syahrul,
Remarks still not in the email details. Kindly assist. Tq
#4 Updated by Syahrul Anwar about 11 years ago
- Status changed from Development / Work In Progress to Finished Development
- % Done changed from 80 to 100
add remarks for email notification
#5 Updated by Lizahwati Basirun about 11 years ago
- Status changed from Finished Development to Development / Work In Progress
Salam Syahrul,
Kindly assist on the add on changes. Should synchronize with RIB that already changed by Anwar and requested by Ayu (Redmine Case #3334)
1. To re-order confirmation & result page field tally with details page:-- New 3rd Party
- Fav 3rd Party
- New Interbank
- Fav Interbank
2. Change validation rules for Beneficiary Holder Name (Interbank Transfer)
Current:
Beneficiary Holder Name is not valid, cannot include numbers and special characters except space.
Expected:
Beneficiary Holder Name is not valid, cannot include numbers and special characters except space.@/
#6 Updated by Lizahwati Basirun about 11 years ago
- % Done changed from 100 to 80
Add On Issue:
- Tested on remarks and it shown on the email but kindly put dash (-) if no remarks input.
#7 Updated by Siti Norahayu Mohd Desa about 11 years ago
Kindly apply the same at RIB as well. TQ
#8 Updated by Syahrul Anwar about 11 years ago
- Status changed from Development / Work In Progress to Finished Development
- % Done changed from 80 to 100
add ''-'' for empty remarks ,,,
add validation for Beneficiary Holder Name interbank
#9 Updated by Syahrul Anwar about 11 years ago
add ''-'' for empty remarks in confirm, result, receipt, email
#10 Updated by Norhaidah Md Dasuki about 11 years ago
- Status changed from Finished Development to Closed - End of life cycle
- Assignee changed from Syahrul Anwar to Norhaidah Md Dasuki
27.07.2013 [Halimah] - Had been retest and OK.