Task #3360

Integration module for ePay

Added by Vincent Devethas about 11 years ago. Updated almost 11 years ago.

Status:Work Completed-End life cycleStart date:August 01, 2013
Priority:NormalDue date:August 06, 2013
Assignee:Norhaidah Md Dasuki% Done:

100%

Category:-Estimated time:12.00 hours
Target version:-Spent time:12.00 hours

Description

  • Create interface to integrate with Host. Composing of request message and send to host. Capture the response from host and take further action accordingly.

History

#1 Updated by Vincent Devethas about 11 years ago

  • Status changed from New - Begin Life Cycle to Development / Work In Progress

#2 Updated by Vincent Devethas about 11 years ago

  • Due date changed from July 29, 2013 to August 06, 2013
  • Status changed from Development / Work In Progress to Internal Testing
  • Start date changed from July 26, 2013 to August 01, 2013
  • % Done changed from 0 to 90

development completed...

#3 Updated by Vincent Devethas about 11 years ago

  • Status changed from Internal Testing to Finished Development

#4 Updated by Vincent Devethas about 11 years ago

  • Status changed from Finished Development to Internal Testing
  • Assignee changed from Vincent Devethas to Norhaidah Md Dasuki
  • % Done changed from 90 to 100

#5 Updated by Norhaidah Md Dasuki almost 11 years ago

  • Status changed from Internal Testing to Work Completed-End life cycle

Intergration test completed on September 5th 2013
Reference: AGRO/RIB/SIT/20130905

Also available in: Atom PDF