Task #3361
RIB: Mobile Report Module
Status: | Work Completed-End life cycle | Start date: | July 29, 2013 | |
---|---|---|---|---|
Priority: | Normal | Due date: | July 31, 2013 | |
Assignee: | Norhaidah Md Dasuki | % Done: | 100% | |
Category: | - | Spent time: | 30.00 hours | |
Target version: | - |
Description
- Create two separate modules: Pinless and Pin Based. Each module divided into a few steps allowing the customers to perform reload. Towards the end of the process, send instruction to host and update into the respective database tables.
History
#1 Updated by Vincent Devethas about 11 years ago
- Assignee changed from Vincent Devethas to Yap Kah Yan
#2 Updated by Vincent Devethas about 11 years ago
- Status changed from New - Begin Life Cycle to Finished Development
- % Done changed from 0 to 100
development completed
#3 Updated by Vincent Devethas about 11 years ago
- Status changed from Finished Development to Internal Testing
- Assignee changed from Yap Kah Yan to Norhaidah Md Dasuki
#4 Updated by Norhaidah Md Dasuki almost 11 years ago
- Status changed from Internal Testing to Work Completed-End life cycle
Finished Development. Assigned to QA for Internal Test under Report Module. Refer #3733