Task #3571

Application (CCPP, online ticketing, im2u sg integration) Customization

Added by Anonymous about 11 years ago. Updated almost 11 years ago.

Status:Work Completed-End life cycleStart date:September 06, 2013
Priority:NormalDue date:September 26, 2013
Assignee:Wong Bernard% Done:

100%

Category:-Spent time:-
Target version:-

Description

Application (CCPP, online ticketing, im2u sg integration)customization to Upass.

History

#1 Updated by Anonymous about 11 years ago

  • Due date changed from September 18, 2013 to September 19, 2013

#2 Updated by Anonymous almost 11 years ago

  • Due date changed from September 19, 2013 to September 26, 2013

Hazrul will handle the im2u sg integration.

CCPP already completed pending for testing

Online ticketing will be complete by 26 sept. targeted to test on 27 sept.

#3 Updated by Wong Bernard almost 11 years ago

  • Status changed from New - Begin Life Cycle to Development / Work In Progress
  • % Done changed from 0 to 50

CCPP ran into implementation issue. Initially believed it was JSP with embedded Java coding, but turns out it was embedded Javascripts.

New implementing required and in the works.

#4 Updated by Anonymous almost 11 years ago

Hazrul will handle for Online ticketing.

#5 Updated by Wong Bernard almost 11 years ago

  • Status changed from Development / Work In Progress to Finished Development
  • % Done changed from 50 to 100

#6 Updated by Tan Lee Yong almost 11 years ago

  • Status changed from Finished Development to Work Completed-End life cycle