Task #4043
CR-00013: Intergration of Ar-Rahnu System New Solution
Status: | Closed - End of life cycle | Start date: | February 10, 2014 | |
---|---|---|---|---|
Priority: | Normal | Due date: | February 14, 2014 | |
Assignee: | Lizahwati Basirun | % Done: | 100% | |
Category: | - | Spent time: | - | |
Target version: | - |
Description
LO: AGB100 Date: 20/12/2013
Internet Banking Inquiry- To add new Sub Navigation under Account and Banking module for Ar Rahnu product in order to allow customer to select when they want to enquire Ar Rahnu account balances
- Add new logic (integration) to pull the information real time from Microlink via direct web service message format and information to be display are:
- Principal Balance outstanding
- Safekeeping Fees outstanding
- Other cost outstanding
Notes: Microlink will return the above information otherwise to return as customer not found and to display “Account not available”
Internet Banking Payment - refer attached propose Ar Rahnu payment process flow.- To add Ar Rahnu account under Own Account Transfer “To Account” dropdown list in order to allow customer to make loan payment for Ar Rahnu.
Notes:
To Account, for the transaction will be checking through Microlink whereby if Microlink return good response, then it’s allow doing the transaction regardless the account status.
Depends to the readiness of integration between Silverlake and Middleware
Related issues
History
#1 Updated by Norhaidah Md Dasuki over 10 years ago
- Assignee changed from Norhaidah Md Dasuki to Yap Kah Yan
Hi Kah Yan,
Kindly proceed the development for this CR.
Branch: CR-00013
Project: rib, bib, ibssCore, esb, upass, upass-client, ws-upass, core-banking, utils
Target to go for SIT/UAT - 14/1/2014
#2 Updated by Yap Kah Yan over 10 years ago
Pending integration document
#3 Updated by Norhaidah Md Dasuki over 10 years ago
- File Agrobank Ar Rahnu Message Mapping v0.7.doc added
- Due date changed from January 10, 2014 to February 14, 2014
- Start date changed from January 02, 2014 to February 10, 2014
Updates documents from Beans.
#4 Updated by Norhaidah Md Dasuki over 10 years ago
- Status changed from New - Begin Life Cycle to Development / Work In Progress
RUZAIMAH SAMAT
Feb 27 (5 days ago)
Berikut adalah link untuk ArRahnu Account Listing & detail.
http://10.6.6.191:8080/ArRahnu/MicrolinkServices?wsdl
Kah Yan,Kindly proceed. Our target to finish development and testing is by 11/3/2014.
#5 Updated by Yap Kah Yan over 10 years ago
- Status changed from Development / Work In Progress to Finished Development
- % Done changed from 0 to 100
Currently in SIT/UAT testing phase
#6 Updated by Norhaidah Md Dasuki over 10 years ago
- Status changed from Finished Development to System Integration Test
#7 Updated by Wijaya Kartono over 10 years ago
Merged into production branch.
#8 Updated by Lizahwati Basirun over 10 years ago
- Status changed from System Integration Test to Pending Prod Deployment
- Assignee changed from Yap Kah Yan to Lizahwati Basirun
Pending for deployment to production. Internal Test Result had upload into Alfresco.
#9 Updated by Lizahwati Basirun over 10 years ago
- Status changed from Pending Prod Deployment to Work Completed-End life cycle
Successfully migrate to production on 16/04/2014 (ID0008)
#10 Updated by Norhaidah Md Dasuki over 10 years ago
- Status changed from Work Completed-End life cycle to Closed - End of life cycle