Bug #438
BCA-DDA-UAT-C020
Status: | Closed - End of life cycle | Start date: | September 01, 2010 | |
---|---|---|---|---|
Priority: | Normal | Due date: | October 08, 2010 | |
Assignee: | Nor Shuhaida Subri | % Done: | 100% | |
Category: | - | Spent time: | 6.00 hours | |
Target version: | - |
Description
Email Notification for Demand Draft
History
#1 Updated by Nor Shuhaida Subri about 14 years ago
- Status changed from New - Begin Life Cycle to Work Completed-End life cycle
- % Done changed from 0 to 100
modified the email alignment for DD inside result service
#2 Updated by Latipah Abdul Rashid almost 14 years ago
- File Retest_Issue_Log_C020_-_Fail.pdf added
- Due date changed from September 02, 2010 to October 06, 2010
- Status changed from Work Completed-End life cycle to New - Begin Life Cycle
Status update by Chooi So Fun on 04/10/2010:
Fail - refer to file attached for details on the amendments
#3 Updated by Tan Lee Yong almost 14 years ago
Please indicate the time spent and also update the due date. This is over due.
#4 Updated by Nor Shuhaida Subri almost 14 years ago
- Due date changed from October 06, 2010 to October 07, 2010
- % Done changed from 100 to 90
#5 Updated by Nor Shuhaida Subri almost 14 years ago
- Due date changed from October 07, 2010 to October 08, 2010
#6 Updated by Nor Shuhaida Subri almost 14 years ago
- % Done changed from 90 to 100
modified the formated email display inside the result service of DD and BC.
#7 Updated by Nor Shuhaida Subri almost 14 years ago
- Status changed from New - Begin Life Cycle to Work Completed-End life cycle
update status New to Resolved
#8 Updated by Hafizudin MD almost 14 years ago
tested by hafiz
status ok
#9 Updated by Latipah Abdul Rashid almost 14 years ago
- Status changed from Work Completed-End life cycle to Closed - End of life cycle
Issue closed by Chooi So Fun on 19.10.10