Status: | Work Completed-End life cycle | Start date: | September 22, 2014 | |
---|---|---|---|---|
Priority: | Normal | Due date: | September 26, 2014 | |
Assignee: | Ngoh Chee Onn | % Done: | 100% | |
Category: | Development | Spent time: | 12.00 hours | |
Target version: | - |
Description
Description: Module for fund transfer from Maybank to different bank
a.Open Fund Transfer
i. Detail page
ii. Confirm page(TAC)
iii. Result page(Print)
b.Favourite Fund Transfer
i. Detail page
ii. Confirm page
iii. Result page(Print)
History
#1 Updated by Anonymous almost 10 years ago
- Due date changed from August 15, 2014 to September 26, 2014
- Assignee changed from Najmi Pasarudin to Ngoh Chee Onn
- Start date changed from August 15, 2014 to September 22, 2014
#2 Updated by Ngoh Chee Onn almost 10 years ago
- Status changed from New - Begin Life Cycle to Development / Work In Progress
- % Done changed from 0 to 90
Finish development for interbank open and favourite fund transfer, but favourite fund transfer still testing on the host message.
Thank you.
#3 Updated by Anonymous almost 10 years ago
- Parent task set to #4747
#4 Updated by Ngoh Chee Onn almost 10 years ago
- Status changed from Development / Work In Progress to Finished Development
- Assignee changed from Ngoh Chee Onn to Norhaidah Md Dasuki
- % Done changed from 90 to 100
Finish development for this module.
Hi Norahayu,
Please perform SIT test on sit environment https://lab.maybank2u.com.kh/KH_RIB_SIT_NEW/common/Login.do
Thank you.
#5 Updated by Anonymous almost 10 years ago
- Status changed from Finished Development to Internal Testing
- Assignee changed from Norhaidah Md Dasuki to Siti Norahayu Mohd Desa
#6 Updated by Siti Norahayu Mohd Desa almost 10 years ago
- File Open & fav Interbank.docx added
- Status changed from Internal Testing to Development / Work In Progress
- Assignee changed from Siti Norahayu Mohd Desa to Ngoh Chee Onn
- % Done changed from 100 to 80
Hi Chee Onn,
Kindly update the interface based on the user request. Please refer attachment. TQ
#7 Updated by Ngoh Chee Onn almost 10 years ago
- Assignee changed from Ngoh Chee Onn to Siti Norahayu Mohd Desa
Hi Norahayu,
Interface update done according to the user request, please test again.
Thank you.
#8 Updated by Siti Norahayu Mohd Desa almost 10 years ago
- Assignee changed from Siti Norahayu Mohd Desa to Ngoh Chee Onn
- % Done changed from 80 to 90
Please change the Box Navigation
Pending to enable Next Navigation to scroll for next menu..
#9 Updated by Tan Lee Yong almost 10 years ago
- Status changed from Development / Work In Progress to Work Completed-End life cycle
- % Done changed from 90 to 100