Task #4725

Task #4770: MCI: Overall Status Tracking

Task #4721: Existing Module - Reskin

Reskin: Account Maintenance

Added by Anonymous about 10 years ago. Updated almost 10 years ago.

Status:Work Completed-End life cycleStart date:September 22, 2014
Priority:NormalDue date:October 10, 2014
Assignee:-% Done:

100%

Category:DevelopmentSpent time:-
Target version:-

Description

Update new template

History

#1 Updated by Anonymous almost 10 years ago

  • Subject changed from Account Maintenance to Reskin: Account Maintenance

#2 Updated by Najmi Pasarudin almost 10 years ago

  • Due date changed from September 22, 2014 to October 03, 2014
  • Status changed from New - Begin Life Cycle to Development / Work In Progress
  • % Done changed from 0 to 80

Require tablet and phone view testing.

#3 Updated by Anonymous almost 10 years ago

  • Status changed from Development / Work In Progress to Internal Testing
  • Assignee changed from Najmi Pasarudin to Siti Norahayu Mohd Desa

Ayu, pls test.

#4 Updated by Siti Norahayu Mohd Desa almost 10 years ago

  • Status changed from Internal Testing to Development / Work In Progress
  • Assignee changed from Siti Norahayu Mohd Desa to Anonymous

The re-skin module still in progress. Pending to re-skin link & Unlink page.

#5 Updated by Anonymous almost 10 years ago

  • Assignee changed from Anonymous to Najmi Pasarudin

Please update.

#6 Updated by Najmi Pasarudin almost 10 years ago

  • Due date changed from October 03, 2014 to October 10, 2014
  • % Done changed from 80 to 100

#7 Updated by Anonymous almost 10 years ago

  • Status changed from Development / Work In Progress to Internal Testing
  • Assignee changed from Najmi Pasarudin to Siti Norahayu Mohd Desa

Ayu,
Pls retest. If found error, pls let Najmi know immediately.

#8 Updated by Siti Norahayu Mohd Desa almost 10 years ago

  • Status changed from Internal Testing to Development / Work In Progress
  • Assignee changed from Siti Norahayu Mohd Desa to Stephanie Sufrapto
  • Priority changed from Normal to Urgent
  • % Done changed from 100 to 90

To add display box at Unlink Account.

#9 Updated by Stephanie Sufrapto almost 10 years ago

  • Assignee changed from Stephanie Sufrapto to Siti Norahayu Mohd Desa
  • Priority changed from Urgent to Normal
  • % Done changed from 90 to 100

Corrected. please check. Thanks

#10 Updated by Siti Norahayu Mohd Desa almost 10 years ago

  • Status changed from Development / Work In Progress to Work Completed-End life cycle
  • Assignee changed from Siti Norahayu Mohd Desa to Anonymous

Amy,
Pending for UAT status not in the list. I change the status to Work Completed. TQ

#11 Updated by Anonymous almost 10 years ago

  • Status changed from Work Completed-End life cycle to Pending UAT Deployment

#12 Updated by Tan Lee Yong almost 10 years ago

  • Status changed from Pending UAT Deployment to Work Completed-End life cycle

Also available in: Atom PDF