Change #4783
[SCP ID :##2454##] : Change Middleware DNS Name for epay & Arrahnu.
Status: | Work Completed-End life cycle | Start date: | October 20, 2014 | |
---|---|---|---|---|
Priority: | Normal | Due date: | ||
Assignee: | Lizahwati Basirun | % Done: | 100% | |
Category: | - | Spent time: | - | |
Target version: | - |
Description
Hi,
Kindly attend below request:
Kindly change the config setting for integration with epay & Ar Rahnu via middleware in productionand DR.
Current Production & DR : #Epay Reload Web Service esb.endpoint.epayreload=http://10.1.1.203:8080/AgroBankESBProject/ebws/EPAYService/EPAYReload esb.endpoint.ar.rahnu=http://PPMIDDLE0A01:8080/ArRahnu/MicrolinkServices?wsdl Change to DNS Name : esb.endpoint.epayreload=http://middleware:8080/AgroBankESBProject/ebws/EPAYService/EPAYReload esb.endpoint.ar.rahnu=http://middleware:8080/ArRahnu/MicrolinkServices?wsdl
History
#1 Updated by Lizahwati Basirun almost 10 years ago
- Assignee changed from Lizahwati Basirun to Wijaya Kartono
Hi Kartono,
Kindly assist to change the setting as per requirement.
Thank you.
#2 Updated by Wijaya Kartono almost 10 years ago
- Status changed from New - Begin Life Cycle to Work Completed-End life cycle
- Assignee changed from Wijaya Kartono to Lizahwati Basirun
- % Done changed from 0 to 100
Hi kak Lizah,
Config setting was changed. Ready for migration. Below are additional changes as per email from Ruzaimah (AGRO IT) on 30 Oct 2014, 5.14 PM.
BIB : Current Production & DR
#-------- SendOut (Email) --------#
sendmailhost= 10.1.1.90
#-------- Global Transaction Limit (RM) --------#
app.global.transaction.limit=6000
Change to DNS Name :
#-------- SendOut (Email) --------#
sendmailhost = mail.agrobank.bpmb.local
#-------- Global Transaction Limit (RM) --------#
app.global.transaction.limit=500000