Status:Work Completed-End life cycleStart date:September 21, 2010
Priority:NormalDue date:September 28, 2010
Assignee:Wong Bernard% Done:

100%

Category:-Estimated time:168.00 hours
Target version:-Spent time:83.00 hours

History

#1 Updated by Wong Bernard about 14 years ago

  1. Coding for accepting eDividend upload file almost completed
  2. Coding for report generation and testing will follow

#2 Updated by Wong Bernard almost 14 years ago

  • % Done changed from 50 to 80
  1. Reports completed
  2. Testing uploading sample eDividend file. Running into inconsistency with BRS file upload specs with actual run time environment

#3 Updated by Wong Bernard almost 14 years ago

  • Status changed from Development / Work In Progress to Work Completed-End life cycle
  • % Done changed from 80 to 100
  1. Successfully uploaded sample eDividend batch file and saved to database.
  2. Require more extensive testing

#4 Updated by Wong Bernard almost 14 years ago

  • % Done changed from 100 to 50
  1. Re-designing eDividend to reuse existing coding better
  2. In the process of merging with Production and EPF BIB projects to reduce errors found in during test script creation

#5 Updated by Wong Bernard almost 14 years ago

  • % Done changed from 50 to 100

#6 Updated by Wong Bernard almost 14 years ago

  1. Added eDividend inquiry in CORUS