Bug #489
Bill Payment Report issue - KFH Trace Id: C009
Status: | Work Completed-End life cycle | Start date: | September 30, 2010 | |
---|---|---|---|---|
Priority: | Immediate | Due date: | October 08, 2010 | |
Assignee: | Latipah Abdul Rashid | % Done: | 100% | |
Category: | - | Spent time: | - | |
Target version: | - |
Description
Chooi reported:
1. 2 Prepaid Trx on 28/09/2010 are not reflected in the Daily Internet Trx Rpt as amounts have been debited from account.
2. In ePay Recon File, there is an additional ASTRO bill pmt trx (RM80). This trx is not reflected in the bill pmt report as well as the Daily Internet Trx Rpt.
History
#1 Updated by Tan Lee Yong almost 14 years ago
- File BillPaymentReport_DAILY_20100928.csv added
- File InternetTransactionReport_DAILY_20100928.csv added
- File KFH100928.csv added
- File MobileReloadReport_DAILY_20100928.csv added
- Status changed from New - Begin Life Cycle to Development / Work In Progress
Sharon provided 4 reports:-
Tip, 4 reports as attached.
Pls investigate ASAP as we need to regen the recon file for epay and do recon with Maxis (extra 2 prepaid tranx debited but not found in recon/internet tranx/prepaid rpt)
#2 Updated by Tan Lee Yong almost 14 years ago
- File Italk.docx added
Kamaruddin provided the BVMC-Italk screen shot on Sep 29, 2010 at 2:01 PM
#3 Updated by Tan Lee Yong almost 14 years ago
- File Prepaid_Trxn_List.xls added
Latipah responded to Chooi and (kfh.support@penril.net,sharon.lai@kfh.com.my,kamaruddin.damiri@kfh.com.my,malarvili.muniandy@kfh.com.my) with the missing records in the attached file on Thu, Sep 30, 2010 at 7:24 PM
#4 Updated by Tan Lee Yong almost 14 years ago
Per Jelson explained the problem might be happened as below:-
Suspect that there is error in BV Data Manager. It only happened in App 1 instance 1, may need to restart server to solve the problem.
#5 Updated by Tan Lee Yong almost 14 years ago
- File KFH100929_Revised_.xls added
- File KFH100928_Revised_.xls added
Chooi requested:-
Hi Vincent,
As spoken, info for the 3 missing prepaid trx that provided by Tip, do include the data for the "last column as per given in ePay recon file (highlighted in yellow)".
#6 Updated by Tan Lee Yong almost 14 years ago
Choois requested for explanation on the root cause on Fri, Oct 1, 2010 at 3:43 PM:-
Dear Tip/Jelson,
Pls let us know what is the root cause for this issue.
#7 Updated by Tan Lee Yong almost 14 years ago
Hi All,
Please do update the status to redmine for issue tracking purpose.
#8 Updated by Latipah Abdul Rashid almost 14 years ago
Jelson replied email on Mon, Oct 4, 2010 at 10:34 AM:
Hi Chooi,
After our investigation, we noticed that there was a problem with one of the element in App Server 1 second instance. It is used for writing data into database and it was not functioning correctly. The reason being is either that instance was not started properly or it crashed for some reason during the particular period of time. We have requested IT Server Admin to perform a restart on the affected instance and we have checked through the transactions on that instance which is working fine now.
Please monitor the ePay transaction for time being just in case it happens again. Thanks.
--
Regards,
Jelson Low
#9 Updated by Latipah Abdul Rashid almost 14 years ago
Prepaid Trxn Issue:
Chooi updated the prepaid trxn is working fine now.
Jelson, that day you ask nazri to remove the unused ws link from PROD sbconsole, but it is not removed yet.
Do we still want to have it remove?
SI delete trxn is included in Recon report issue:
SI delete trxn should not be include in the recon report. Will check on it.
#10 Updated by Latipah Abdul Rashid almost 14 years ago
- Status changed from Development / Work In Progress to User Acceptance Test
- % Done changed from 0 to 100
Related to issue production C010. Danniell has fixed it and migrated to STG.
#11 Updated by Latipah Abdul Rashid almost 14 years ago
- Status changed from User Acceptance Test to Pending Prod Deployment
Refer Bug #564 (C010 - ePay Recon File) for sign off
Tested by changing status of failed prepaid trxn to Successful before generating report.
Received sign-off on Nov 15 by Chooi So Fun.
Planned to be migrated to PRODUCTION on Friday 19/11/2010 (together with IBG 2nd Validation migration)
#12 Updated by Latipah Abdul Rashid almost 14 years ago
- Status changed from Pending Prod Deployment to Dropped-End of life cycle
#13 Updated by Latipah Abdul Rashid almost 14 years ago
- Status changed from Dropped-End of life cycle to Work Completed-End life cycle
Couldn't find status = Closed. Set as 'Work Completed'.