Task #4922

Task #4823: MCI: UAT Tracking

Issue 11

Added by Najmi Pasarudin almost 10 years ago. Updated almost 10 years ago.

Status:Work Completed-End life cycleStart date:November 19, 2014
Priority:NormalDue date:November 20, 2014
Assignee:Tan Lee Yong% Done:

100%

Category:UATSpent time:-
Target version:-

Description

Previous button not working. Click on Previous will go to result page.

History

#1 Updated by Najmi Pasarudin almost 10 years ago

  • Status changed from New - Begin Life Cycle to Internal Testing
  • Assignee changed from Najmi Pasarudin to Siti Norahayu Mohd Desa

Previous button on page 2 has been updated.

#2 Updated by Siti Norahayu Mohd Desa almost 10 years ago

  • Subject changed from Issue - Own Account Transfer to Issue 11

Module Fund Transfer > Own Account Transfer

#3 Updated by Siti Norahayu Mohd Desa almost 10 years ago

  • Status changed from Internal Testing to User Acceptance Test
  • Assignee changed from Siti Norahayu Mohd Desa to Tan Lee Yong
  • % Done changed from 0 to 100

Tested & Passed.

#4 Updated by Siti Norahayu Mohd Desa almost 10 years ago

  • Status changed from User Acceptance Test to Work Completed-End life cycle

Issue closed on 21/11/14