Task #4946
Payment errors - cosmetic change
Status: | Work Completed-End life cycle | Start date: | November 24, 2014 | |
---|---|---|---|---|
Priority: | Normal | Due date: | ||
Assignee: | Tan Lee Yong | % Done: | 100% | |
Category: | UAT | Spent time: | - | |
Target version: | - |
History
#1 Updated by Stephanie Sufrapto almost 10 years ago
- Status changed from New - Begin Life Cycle to Development / Work In Progress
#2 Updated by Stephanie Sufrapto almost 10 years ago
- Status changed from Development / Work In Progress to Internal Testing
- % Done changed from 0 to 90
Fixed. Deployed on SIT and UAT.
#3 Updated by Stephanie Sufrapto almost 10 years ago
- Assignee changed from Stephanie Sufrapto to Siti Norahayu Mohd Desa
#4 Updated by Siti Norahayu Mohd Desa almost 10 years ago
- Status changed from Internal Testing to Work Completed-End life cycle
- Assignee changed from Siti Norahayu Mohd Desa to Tan Lee Yong
- % Done changed from 90 to 100
Tested. Cosmetic changed as per request.