Task #4970
Task #4823: MCI: UAT Tracking
Issue 81 : Open Cardless Withdrawal
Status: | Work Completed-End life cycle | Start date: | November 26, 2014 | |
---|---|---|---|---|
Priority: | Normal | Due date: | November 26, 2014 | |
Assignee: | Tan Lee Yong | % Done: | 100% | |
Category: | UAT | Spent time: | - | |
Target version: | - |
Description
System don’t prompt error message, "From Account is required".
History
#1 Updated by Siti Norahayu Mohd Desa almost 10 years ago
- Parent task set to #4823
#2 Updated by Najmi Pasarudin almost 10 years ago
- Status changed from New - Begin Life Cycle to Internal Testing
- Assignee changed from Najmi Pasarudin to Siti Norahayu Mohd Desa
Code fixed. Error label was incorrect.
#3 Updated by Siti Norahayu Mohd Desa almost 10 years ago
- Status changed from Internal Testing to Work Completed-End life cycle
- Assignee changed from Siti Norahayu Mohd Desa to Tan Lee Yong
- % Done changed from 0 to 100
Tested & Passed. Send for UAT
User closed issue on 27/11/14