Task #4995
Task #4823: MCI: UAT Tracking
Issue 126: Favorite Interbank Fund Transfer
Status: | Work Completed-End life cycle | Start date: | December 02, 2014 | |
---|---|---|---|---|
Priority: | Normal | Due date: | December 02, 2014 | |
Assignee: | Tan Lee Yong | % Done: | 100% | |
Category: | UAT | Spent time: | - | |
Target version: | - |
Description
- Favorite Interbank Fund Transfer - Can reach step 2 of 4 without Beneficiary Detail.
- There is no Field Beneficiary Account Numbers.
History
#1 Updated by Stephanie Sufrapto almost 10 years ago
- Status changed from New - Begin Life Cycle to Finished Development
- % Done changed from 0 to 90
Fixed and deployed on UAT and SIT
#2 Updated by Siti Norahayu Mohd Desa almost 10 years ago
- Status changed from Finished Development to User Acceptance Test
- Assignee changed from Stephanie Sufrapto to Siti Norahayu Mohd Desa
- % Done changed from 90 to 100
Send for UAT Testing
#3 Updated by Siti Norahayu Mohd Desa almost 10 years ago
- Status changed from User Acceptance Test to Work Completed-End life cycle
- Assignee changed from Siti Norahayu Mohd Desa to Tan Lee Yong
Issue Closed by user on 03.12.2014