Task #5006
Task #4823: MCI: UAT Tracking
Issue 147: Cardless Withdrwal - Favourite Cardless Withdrawal
Status: | Work Completed-End life cycle | Start date: | December 03, 2014 | |
---|---|---|---|---|
Priority: | Normal | Due date: | December 03, 2014 | |
Assignee: | Tan Lee Yong | % Done: | 100% | |
Category: | UAT | Spent time: | - | |
Target version: | - |
Description
Favorite Cardless Withdrawal - There is no ADD Hyperlink for adding new favorite.
History
#1 Updated by Najmi Pasarudin almost 10 years ago
- Status changed from New - Begin Life Cycle to Internal Testing
- Assignee changed from Najmi Pasarudin to Siti Norahayu Mohd Desa
#2 Updated by Siti Norahayu Mohd Desa almost 10 years ago
- Status changed from Internal Testing to User Acceptance Test
- % Done changed from 0 to 100
Send for UAT Testing
#3 Updated by Siti Norahayu Mohd Desa almost 10 years ago
- Status changed from User Acceptance Test to Work Completed-End life cycle
- Assignee changed from Siti Norahayu Mohd Desa to Tan Lee Yong
Issue Closed by user on 03.12.2014