Test Ref# 1.1: Event Listing
Status: | Work Completed-End life cycle | Start date: | October 05, 2015 | |
---|---|---|---|---|
Priority: | Normal | Due date: | October 06, 2015 | |
Assignee: | Siti Norahayu Mohd Desa | % Done: | 100% | |
Category: | TPMS_Test | Spent time: | - | |
Target version: | - |
Description
To change List of Activities Start Date & End Date format to dd/mm/yyyy.
History
#1 Updated by Ngoh Chee Onn almost 9 years ago
- Assignee changed from Ngoh Chee Onn to Siti Norahayu Mohd Desa
Changes done. Please try again.
Thank you.
#2 Updated by Siti Norahayu Mohd Desa almost 9 years ago
- Status changed from New - Begin Life Cycle to Work Completed-End life cycle
- % Done changed from 0 to 100
07/10/15 [Ayu] - Tested & Passed