Bug #5719

[UAT3-9/009] - Promotion > Reports > Date Range

Added by Siti Norahayu Mohd Desa almost 9 years ago. Updated almost 9 years ago.

Status:Closed - End of life cycleStart date:November 23, 2015
Priority:NormalDue date:November 24, 2015
Assignee:Siti Norahayu Mohd Desa % Done:

100%

Category:tpms_uatSpent time:-
Target version:-

Description

If choose date range - system not clear old data history

History

#1 Updated by Siti Norahayu Mohd Desa almost 9 years ago

  • Subject changed from [UAT3-9/009] - Promotion > Reports to [UAT3-9/009] - Promotion > Reports > Date Range

#2 Updated by Siti Norahayu Mohd Desa almost 9 years ago

  • Assignee changed from Shahidan Syahirman to Ngoh Chee Onn

#3 Avatar?id=1966&size=24 Updated by Ngoh Chee Onn almost 9 years ago

  • Assignee changed from Ngoh Chee Onn to Siti Norahayu Mohd Desa

If choose date range - system not clear old data history - Fixed, please try again after deployment.

Thank you.

#4 Updated by Siti Norahayu Mohd Desa almost 9 years ago

  • Status changed from New - Begin Life Cycle to User Acceptance Test
  • % Done changed from 0 to 100

25/11/15 [Ayu]
Tested & Passed. Send for user testing.

#5 Updated by Siti Norahayu Mohd Desa almost 9 years ago

  • Status changed from User Acceptance Test to Development / Work In Progress
  • Assignee changed from Siti Norahayu Mohd Desa to Tan Jeng Wei
  • % Done changed from 100 to 90

16/12/15 - Issue re-open by user.

To hide calendar after click month and day for Start Date.

Step to re-produce
  1. Promotion > Reports > Date Range
  2. Choose Date range
  3. Click on Start Date
  4. After choose month and day calendar not disappear.

#6 Updated by Tan Jeng Wei almost 9 years ago

  • Status changed from Development / Work In Progress to Internal Testing
  • Assignee changed from Tan Jeng Wei to Siti Norahayu Mohd Desa

hi ayu

root/cause: datapicker selected function is not working
solution : changing datapicker selected function
please test it after deployed...Thanks a lot.

#7 Updated by Siti Norahayu Mohd Desa almost 9 years ago

  • Status changed from Internal Testing to User Acceptance Test
  • % Done changed from 90 to 100

16/12/15 [Ayu]
tested and send to user for testing

#8 Updated by Norhaidah Md Dasuki almost 9 years ago

  • Status changed from User Acceptance Test to Closed - End of life cycle

15/12/15 - Issue Closed.

Also available in: Atom PDF