Bug #5731

[UAT3-9/035] - Post Event > Programmes > Budget Utilization

Added by Siti Norahayu Mohd Desa almost 9 years ago. Updated over 8 years ago.

Status:Closed - End of life cycleStart date:November 24, 2015
Priority:NormalDue date:November 25, 2015
Assignee:Siti Norahayu Mohd Desa % Done:

100%

Category:tpms_uatSpent time:-
Target version:-

Description

1) Updated information was not save successfully
2) No comma in numbering

History

#1 Avatar?id=1966&size=24 Updated by Ngoh Chee Onn almost 9 years ago

  • Assignee changed from Ngoh Chee Onn to Siti Norahayu Mohd Desa

For case no 1 - Which information not save?

Thank you.

#2 Avatar?id=1966&size=24 Updated by Ngoh Chee Onn almost 9 years ago

1) Updated information was not save successfully - Found that total utilization amount not save, fixed.
2) No comma in numbering - fixed.

Please test again after deployment for those mark as fixed.

Thank you.

#3 Updated by Siti Norahayu Mohd Desa almost 9 years ago

  • Status changed from New - Begin Life Cycle to Development / Work In Progress
  • Assignee changed from Siti Norahayu Mohd Desa to Ngoh Chee Onn
  • % Done changed from 0 to 50
Budget Allocated > Edit
  1. To add monetary format for Allocated column value
  2. Please apply label Budget in Budget Column as in view page.

#4 Avatar?id=1966&size=24 Updated by Ngoh Chee Onn almost 9 years ago

  • Assignee changed from Ngoh Chee Onn to Siti Norahayu Mohd Desa

Fixed done, please try again after deployment.

Thank you.

#5 Updated by Siti Norahayu Mohd Desa almost 9 years ago

  • Status changed from Development / Work In Progress to User Acceptance Test
  • % Done changed from 50 to 100

25/11/15 [Ayu]
Tested & Passed. Send for user testing.

#6 Updated by Norhaidah Md Dasuki over 8 years ago

  • Status changed from User Acceptance Test to Closed - End of life cycle

15/12/15 - Issue Closed

Also available in: Atom PDF