Bug #5735
[UAT3-9/040] - Dashboard > Budget
Status: | Closed - End of life cycle | Start date: | November 24, 2015 | |
---|---|---|---|---|
Priority: | Urgent | Due date: | November 25, 2015 | |
Assignee: | Siti Norahayu Mohd Desa | % Done: | 100% | |
Category: | tpms_uat | Spent time: | - | |
Target version: | - |
Description
1) Budget by region only shows 2 region (ASEAN & MIDDLE EAST)
2) Budget by Section only shows 3 sections. Section shall display in english
3) Budget by sector only shows 3 section
4) Budget program only shows 2 program
History
#1 Updated by Shahidan Syahirman almost 9 years ago
- Assignee changed from Shahidan Syahirman to Siti Norahayu Mohd Desa
hi akak ayu,
i already check and confirmed with najmi.
the reason chart data is not cater with the planning activities list is because the data within the activities list is not completed. to ensure the data integrity within the chart, eb_id which referring to budget type must co exist with ed_budget_approved (Budget type). budget type cannot be null.
please check.
thank you
#2 Updated by Shahidan Syahirman almost 9 years ago
fix section name from bahasa melayu to english.
#3 Updated by Norhaidah Md Dasuki almost 9 years ago
- Status changed from New - Begin Life Cycle to Internal Testing
#4 Updated by Lim Leonard almost 9 years ago
- Status changed from Internal Testing to Work Completed-End life cycle
#5 Updated by Siti Norahayu Mohd Desa almost 9 years ago
- Status changed from Work Completed-End life cycle to User Acceptance Test
- % Done changed from 0 to 100
13/12/15 [Leo]
Tested & Passed.
Send for user testing.
#6 Updated by Norhaidah Md Dasuki over 8 years ago
- Status changed from User Acceptance Test to Closed - End of life cycle
15/12/15 - Issue Closed