Bug #5836
[PN RAJA] Dashboard - Overall
Status: | Work Completed-End life cycle | Start date: | December 13, 2015 | |
---|---|---|---|---|
Priority: | Normal | Due date: | ||
Assignee: | Lim Leonard | % Done: | 100% | |
Category: | - | Spent time: | - | |
Target version: | - |
Description
- to change the name "OTHER" to "OTHERS"
- to put the currency "RM" in the amount of the chart, when the mouse point on the chart
- to change "MYR" to "RM"
- to reduce the 000.000. eg. RM (In Millions)
- to sort the name of the Section Alphabetically
- to only show/display the event with the status 'CONFIRM' and above
History
#1 Updated by Lim Leonard almost 9 years ago
- Assignee changed from Shahidan Syahirman to Aditya Prathama
#2 Updated by Aditya Prathama almost 9 years ago
- Status changed from New - Begin Life Cycle to Internal Testing
- Assignee changed from Aditya Prathama to Lim Leonard
- % Done changed from 0 to 100
Bug fixed please test,
#3 Updated by Lim Leonard almost 9 years ago
- Status changed from Internal Testing to Development / Work In Progress
- Assignee changed from Lim Leonard to Aditya Prathama
- to reduce the 000.000. eg. RM (In Millions)
to clarify the 'RM' into 'RM (in Millions)'
- to sort the name of the Section Alphabetically
#4 Updated by Aditya Prathama almost 9 years ago
- Status changed from Development / Work In Progress to Internal Testing
- Assignee changed from Aditya Prathama to Lim Leonard
Please retest after deploy
#5 Updated by Lim Leonard almost 9 years ago
- Status changed from Internal Testing to Development / Work In Progress
- Assignee changed from Lim Leonard to Aditya Prathama
#6 Updated by Aditya Prathama almost 9 years ago
- Status changed from Development / Work In Progress to Internal Testing
- Assignee changed from Aditya Prathama to Lim Leonard
please retest afterdeploy
#7 Updated by Lim Leonard almost 9 years ago
- Status changed from Internal Testing to Work Completed-End life cycle