Support #5984
[TPMS_Prod068] - Post Event > JPPPA Report > Report - PROGRAMME BY MINISTRY
Status: | Closed - End of life cycle | Start date: | February 22, 2016 | |
---|---|---|---|---|
Priority: | Normal | Due date: | February 22, 2016 | |
Assignee: | Norhaidah Md Dasuki | % Done: | 100% | |
Category: | tpms_prod | Spent time: | - | |
Target version: | - |
Description
To complete the ministry name. e.g. “KKR” >> “Ministry of Work (KKR)”.
History
#1 Updated by Tan Jeng Wei over 8 years ago
- Status changed from New - Begin Life Cycle to Internal Testing
- % Done changed from 0 to 90
#2 Updated by Tan Jeng Wei over 8 years ago
- Assignee changed from Tan Jeng Wei to Siti Norahayu Mohd Desa
Hi Ayu,
Root Cause: Taking data from r_ministry_abbr columns.
Solution : Change the r_ministry_abbr columns to r_ministry_eng columns.
Please retest after deployed from (Enhancement Branch). Thanks a lot.
#3 Updated by Siti Norahayu Mohd Desa over 8 years ago
- Subject changed from [TPMS_Prod068] - Post Event > JPPPA Report > Fast Facts > No. of programme by Ministry to [TPMS_Prod068] - Post Event > JPPPA Report > Report - PROGRAMME BY MINISTRY
- Status changed from Internal Testing to Development / Work In Progress
- Assignee changed from Siti Norahayu Mohd Desa to Tan Jeng Wei
Hi Jeng Wei,
Kindly assist to display the name as per request.
Example : Ministry of Works (KKR)
#4 Updated by Tan Jeng Wei over 8 years ago
- File Reports.pdf added
- File Reports.xls added
- Status changed from Development / Work In Progress to Internal Testing
- Assignee changed from Tan Jeng Wei to Siti Norahayu Mohd Desa
Hi ayu.
Fix the display Name format. Please retest after deployed. Thanks alot.
#5 Updated by Siti Norahayu Mohd Desa over 8 years ago
- File Support#5984_Test Result-TPMS_Prod068.docx added
- Status changed from Internal Testing to User Acceptance Test
- Assignee changed from Siti Norahayu Mohd Desa to Norhaidah Md Dasuki
- % Done changed from 90 to 100
Salam Akak,
Please find test result as per attached.
#6 Updated by Siti Norahayu Mohd Desa over 8 years ago
- Status changed from User Acceptance Test to Pending Prod Deployment
Issue have been tested by Helmi on 26/02/2016. Issue ready to deploy to production.
#7 Updated by Norhaidah Md Dasuki over 8 years ago
- Status changed from Pending Prod Deployment to Pending Customer Feedback
26/2/16 - Migrated to production (War File - ver.010)
4/3/16 [Haida] - Send for verification in Production after deployment
#8 Updated by Norhaidah Md Dasuki over 8 years ago
- Status changed from Pending Customer Feedback to Closed - End of life cycle
5/3/16 [Ayu] - Issue Closed by Helmi