Support #6084
[TPMS_Prod095] - Post Event > JPPPA Report - Outcome / Impact by Programme Type (Detailed)
Status: | Closed - End of life cycle | Start date: | March 16, 2016 | |
---|---|---|---|---|
Priority: | High | Due date: | ||
Assignee: | Norhaidah Md Dasuki | % Done: | 100% | |
Category: | tpms_prod | Spent time: | - | |
Target version: | - |
Description
To fix below issue: (refer attachment for further details
1. "outcome impact programme type (detailed)" pdf - to only display 'other impact' in 'other impact' field
2. "outcome impact programme type (detailed)" excel -'other impact' field is mising,
3. "outcome impact programme type (detailed)" excel -'other impact' is not included in 'impact / feedback' field
4. "outcome impact programme type (detailed)" pdf -'other impact' is not included in 'impact feedback' field
History
#1 Updated by Norhaidah Md Dasuki over 8 years ago
- File deleted (
TPMS - Prod_Issue Log ID 075.docx)
#2 Updated by Norhaidah Md Dasuki over 8 years ago
- File TPMS - Prod_Issue Log ID 095.docx added
- Subject changed from [TPMS_Prod075] - Post Event > JPPPA Report - Outcome / Impact by Programme Type (Detailed) to [TPMS_Prod095] - Post Event > JPPPA Report - Outcome / Impact by Programme Type (Detailed)
#3 Updated by Tan Jeng Wei over 8 years ago
- Assignee changed from Tan Jeng Wei to Lim Leonard
- % Done changed from 0 to 90
Hi Leo,
root/cause: using the Same impact StringBuffer which is requested delete the other columns values into impact columns
Solution : set other impact by using other StringBuffer.
Please retest after deployed. Thanks a lot.
#4 Updated by Lim Leonard over 8 years ago
- File Support#6084_Test Result-TPMS_Prod075.docx added
- Status changed from New - Begin Life Cycle to Pending Review
- Assignee changed from Lim Leonard to Siti Norahayu Mohd Desa
test result attached
#5 Updated by Norhaidah Md Dasuki over 8 years ago
- Status changed from Pending Review to User Acceptance Test
23/3/16 - Send for user retest
#6 Updated by Norhaidah Md Dasuki over 8 years ago
- Status changed from User Acceptance Test to Internal Testing
- Assignee changed from Siti Norahayu Mohd Desa to Lim Leonard
25/3/2016 [Helmi]- Feedback
3. "outcome impact programme type (detailed)" excel -'other impact' is not included in 'impact / feedback' field - Not Fixed
4. "outcome impact programme type (detailed)" pdf -'other impact' is not included in 'impact feedback' field - Not Fixed
Hi Leo, Kindly verify and assigned for fixing if necessary.
#7 Updated by Lim Leonard over 8 years ago
- Status changed from Internal Testing to Development / Work In Progress
- Assignee changed from Lim Leonard to Tan Jeng Wei
Hi Jeng Wei,
Please fix issue #3 and #4,
Thanks
#8 Updated by Tan Jeng Wei over 8 years ago
- Assignee changed from Tan Jeng Wei to Najmi Pasarudin
Hi najimi,
Please help take a look. Urgent issues -
#9 Updated by Najmi Pasarudin over 8 years ago
- Status changed from Development / Work In Progress to Internal Testing
- Assignee changed from Najmi Pasarudin to Siti Norahayu Mohd Desa
Fixed issue:
3. "outcome impact programme type (detailed)" excel -'other impact' is not included in 'impact / feedback' field
4. "outcome impact programme type (detailed)" pdf -'other impact' is not included in 'impact feedback' field
- Download report "outcome impact programme type (detailed)"
- Check column "impact/feedback" and "other impact".
Expected result:
Column "impact/feedback" should show detail such as sales and other impact.
Column "other impact" should show only other impact detail.
#10 Updated by Siti Norahayu Mohd Desa over 8 years ago
- Assignee changed from Siti Norahayu Mohd Desa to Lim Leonard
HI Leo,
Kindly assist.
#11 Updated by Lim Leonard over 8 years ago
- File deleted (
Support#6084_Test Result-TPMS_Prod075.docx)
#12 Updated by Lim Leonard over 8 years ago
- File Support#6084_Test Result-TPMS_Prod075.docx added
- Status changed from Internal Testing to Pending Review
- Assignee changed from Lim Leonard to Siti Norahayu Mohd Desa
test result attached
#13 Updated by Norhaidah Md Dasuki over 8 years ago
- Status changed from Pending Review to Pending Prod Deployment
- Assignee changed from Siti Norahayu Mohd Desa to Norhaidah Md Dasuki
- % Done changed from 90 to 100
4/4/16 - Send for user retest
27/4/16 [Helmi] - "outcome impact programme type (detailed)" excel and PDF -'other impact' is included in 'impact / feedback' field. Case closed
Pending for Prod Deployment
#14 Updated by Norhaidah Md Dasuki over 8 years ago
- Status changed from Pending Prod Deployment to Pending Customer Feedback
11/5/16 - Successfully deployed to production on 8/4/16. Please verify.
Migration (War File): 026/080416
#15 Updated by Norhaidah Md Dasuki over 8 years ago
- Status changed from Pending Customer Feedback to Closed - End of life cycle
25/5/2016 - Closed this issue. No feedback from user after deployment. Send email to verify on 11/5/16 - Subject: Matrade TPMS Cut Off Issue Status up to date