Bug #6207
Change #6054: [UAT1&2 - UAT_122] - Planning >> Activities List
Planning >> Activities List - Total Sales Generated
Status: | Work Completed-End life cycle | Start date: | April 20, 2016 | |
---|---|---|---|---|
Priority: | Normal | Due date: | April 21, 2016 | |
Assignee: | Siti Norahayu Mohd Desa | % Done: | 100% | |
Category: | CR_Phase1 | Spent time: | - | |
Target version: | - |
Description
To check on Data query for "Total Sales Generated" column.
Used below event as reference to ensure data is correct:
1) THE BIG 5 SHOWS 2016 > No feedback form replied but Sales Generated shows 500000.00
2) MIHAS 2016 > Sales Generated did not shows any value (even though the feedback form already input)
History
#1 Updated by Norhaidah Md Dasuki over 8 years ago
- Subject changed from Planning >> Activities List to Planning >> Activities List - Total Sales Generated
#2 Updated by Aditya Prathama over 8 years ago
- Assignee changed from Aditya Prathama to Najmi Pasarudin
#3 Updated by Najmi Pasarudin over 8 years ago
- Status changed from New - Begin Life Cycle to Development / Work In Progress
- % Done changed from 0 to 90
Added function to update sales on view.
#4 Updated by Najmi Pasarudin over 8 years ago
- Assignee changed from Najmi Pasarudin to Tan Jeng Wei
Hi Jeng Wei,
Please help on this issue. The original issue already fixed. But when compared with Dashboard Generated Sales on MITI, the sales not tally with Planning JPPPA export report.
#5 Updated by Tan Jeng Wei over 8 years ago
- Status changed from Development / Work In Progress to Internal Testing
- Assignee changed from Tan Jeng Wei to Siti Norahayu Mohd Desa
Hi Ayu,
Data was tally since adit was changing the view table on ytd. Please check with this. Thanks a lot.
#6 Updated by Siti Norahayu Mohd Desa over 8 years ago
- Status changed from Internal Testing to Work Completed-End life cycle
- % Done changed from 90 to 100
Testing using MIHAs 2016.
Sales generated calculated with an exact amount. (Actual Sales + Potential Sales)