Task #660
AgroBank POC
Status: | Work Completed-End life cycle | Start date: | December 09, 2010 | |
---|---|---|---|---|
Priority: | Normal | Due date: | December 17, 2010 | |
Assignee: | Ahmad Hazri | % Done: | 100% | |
Category: | - | Spent time: | 8.00 hours | |
Target version: | - |
Description
Activity purpose: Simulate at DELL center for AgroBank requirement
Initial test also will be take place at local PC
Platform: Windows Server 2008 x86_64
Application Server : Jboss 5.x.x
Web Server : IIS7
DB Server : SQL Server
Application deploy: Corus
History
#1 Updated by Ahmad Hazri almost 14 years ago
- Status changed from New - Begin Life Cycle to Development / Work In Progress
- % Done changed from 0 to 20
Simulate at local PC (x86)
Platform: Windows Server 2008
Web Server: IIS7
App server: Jboss 510
DB Server : SQL Server 2008 Express Edition
#2 Updated by Ahmad Hazri almost 14 years ago
- % Done changed from 20 to 30
Prerequisite
SQL Server 2008 Express Edition- Power Shell
- .NET Framework 3.5 SP1
- ISAPI filter
- ISAPI extension
- isapi_redirect.dll (bin)
- isapi_redirect.properties (bin)
- workers.properties (conf)
- uriworkermap.properties (conf)
- isapi_redirect.log (log)
- JBoss 5.1.0 installer
- JDK 1.5_x
- CORUS
#3 Updated by Ahmad Hazri almost 14 years ago
- % Done changed from 30 to 40
What is done?
- SQL Server 2008 Express Edition - Installed
- JBOSS and JDK - Installed
- IIS - Installed
- Tomcat Connector (mod_JK)plug-in - Installed
- IIS + Tomcat connector - Configured
Testing
IIS + Tomcat connector >> Jboss - works as expected.
Next?
Configure SQL server and CORUS
This one need help from Vincent who currently busy with other projects and tasks.
This will do later once everything above configured @DELL
#4 Updated by Ahmad Hazri about 12 years ago
- Status changed from Development / Work In Progress to Work Completed-End life cycle
- % Done changed from 40 to 100