Support #6786

[TPMS_GL067] - Planning JPPPA

Added by Siti Norahayu Mohd Desa almost 8 years ago. Updated almost 8 years ago.

Status:Work Completed-End life cycleStart date:November 14, 2016
Priority:NormalDue date:November 16, 2016
Assignee:Najmi Pasarudin% Done:

100%

Category:GO_LiveSpent time:-
Target version:-

Description

I would like to report error related to JPPPA planning activities,

I have created External User account for JPPPA. The account has been set to "Ministry : MINISTRY OF AGRICULTURE AND AGRO-BASED INDUSTRY " and "Agencies : FAMA."

When user view JPPPA programme for 2017 as details below, there are additional 2 entries from other ministry that being displayed. Information being displayed as per below.

Year selection :2017
Planning >> Planning JPPPA :3 entries (2 entries from KPDNKK, 1 from FAMA)
Post Event >> JPPPA Programmes :1 entries (FAMA)

The user should not be able to view entries from KPDNKK.

Attached below is screenshot for Planning >> Planning JPPPA (year selection 2017)

GL067 - Error_ JPPPA Programme Listing (Planning JPPPA module).pdf (4.81 KB) Siti Norahayu Mohd Desa , November 14, 2016 17:07

History

#1 Updated by Najmi Pasarudin almost 8 years ago

  • Status changed from New - Begin Life Cycle to Development / Work In Progress
  • % Done changed from 0 to 10

#2 Updated by Siti Norahayu Mohd Desa almost 8 years ago

  • Subject changed from [TPMS_GL066] - Planning JPPPA to [TPMS_GL067] - Planning JPPPA

#3 Updated by Najmi Pasarudin almost 8 years ago

  • Status changed from Development / Work In Progress to Internal Testing
  • Assignee changed from Najmi Pasarudin to Siti Norahayu Mohd Desa
  • % Done changed from 10 to 90

Issue:
Planning JPPPA search not filtering event based on external user ministry/agency.

Cause:
Search form did not read user ministry/agency properly and search all event.

Solution:
Fix search form to search based on external user ministry/agency.

Test scenario:
  1. Create JPPPA 2 events in 2017. ie event with agency FAMA and event with agency KPDNKK
  2. Login as external user with agency FAMA.
  3. Access Planning > Planning JPPPA.
  4. Click search and search for event in 2017.
  5. Expected result, search result shows only event with agency FAMA.

#4 Updated by Siti Norahayu Mohd Desa almost 8 years ago

  • Status changed from Internal Testing to Pending Customer Feedback
  • % Done changed from 90 to 100

Send for user testing

#5 Updated by Siti Norahayu Mohd Desa almost 8 years ago

  • Status changed from Pending Customer Feedback to Pending Prod Deployment
  • Assignee changed from Siti Norahayu Mohd Desa to Najmi Pasarudin

Dear Siti Norahayu,

I have retest the scenario at UAT server. The listing / expected outcome from test scenario is correct.

Regards,
Mohd Helmi Abdul Shukur
Application Development Unit
eBusiness & IT Section
MATRADE
Tel : 03 - 6207 7077 ext 7332

Hi Najmi,

Please prepare migration document and war file for production deployment.

Migration Plan ID: TPMS_ID0018
War File: TPMS_v047

#6 Updated by Najmi Pasarudin almost 8 years ago

  • Status changed from Pending Prod Deployment to Work Completed-End life cycle

Migration ID: TPMS_ID0018
War File: TPMS_v047
Planned date: 25/11/2016
Deployed date: 28/11/2016

Delayed due to event day on 26 and 27 November 2016.