Status:Work Completed-End life cycleStart date:November 29, 2016
Priority:NormalDue date:November 29, 2016
Assignee:Tommy Arryandy % Done:

0%

Category:WM-SITSpent time:3.00 hours
Target version:-

Description

Dear all,

New issue found during regression:

Issue: When moving from details to confirm page, RMBP shows "System Currently Unavailable"

Thank you.

History

#1 Avatar?id=2607&size=24 Updated by Rayvandy Gabbytian almost 8 years ago

  • Status changed from New - Begin Life Cycle to Development / Work In Progress
  • % Done changed from 0 to 100

Dear all,

Root cause:
- In mobile reload confirm service, there was no need to enquire information from host. However, since PLN enhancement, PLN Prepaid need to enquire message to host by sending processing code. To build processing code it needs the fromAccountNo and fromAccountMap. In RMBP, fromAccountMap is not set. That's why it is giving exception.

Solution:
- Separate 2 channels. If it is called from RMBP, then get fromAccountNo instead fromAccountMap
- When PLN enhancement is done for RMBP, this checknig must be improved.

Thank you.

#2 Avatar?id=2607&size=24 Updated by Rayvandy Gabbytian almost 8 years ago

  • Status changed from Development / Work In Progress to Internal Testing
  • Assignee changed from Rayvandy Gabbytian to Tommy Arryandy
  • % Done changed from 100 to 0

Dear Tommy,

Please pull middle service, deploy restful and test.

Upload the test result in google drive and SIT server and copy the link here.

Thank you.

#3 Updated by Tommy Arryandy over 7 years ago

  • Status changed from Internal Testing to Pending Prod Deployment

Dear all,

PROD deployment for RMBP at 21st December 2017 was canceled/not planned by IT. Not sure what is the reason.

Thus, this fixes has not yet been applied into production.

Thank you.

#4 Updated by Tommy Arryandy about 7 years ago

  • Status changed from Pending Prod Deployment to Work Completed-End life cycle

Already deployed to production