Bug #7206

[TPMS CR201702] - Feedback Form >> Follow Up

Added by Siti Norahayu Mohd Desa over 7 years ago. Updated over 7 years ago.

Status:Work Completed-End life cycleStart date:February 28, 2017
Priority:NormalDue date:March 01, 2017
Assignee:Siti Norahayu Mohd Desa % Done:

100%

Category:TPMS_TestSpent time:-
Target version:-

Description

Please apply the CR requirement to Follow Up feedback form as below:-
TF & EAM
  • Follow Up Blank Form
  • Follow Up from Participating Company

History

#1 Updated by Siti Norahayu Mohd Desa over 7 years ago

  • Description updated (diff)

#2 Updated by Najmi Pasarudin over 7 years ago

  • Status changed from New - Begin Life Cycle to Development / Work In Progress

#3 Updated by Najmi Pasarudin over 7 years ago

  • Status changed from Development / Work In Progress to Internal Testing
  • Assignee changed from Najmi Pasarudin to Siti Norahayu Mohd Desa
  • % Done changed from 0 to 60

Please test:

  1. TF follow-up edit
  2. TF follow-up view
  3. EAM follow-up edit
  4. EAM follow-up view

#4 Updated by Siti Norahayu Mohd Desa over 7 years ago

  • Status changed from Internal Testing to Development / Work In Progress
  • Assignee changed from Siti Norahayu Mohd Desa to Najmi Pasarudin

TF follow-up edit
- Tested & Passed

TF follow-up view
- Potential sales not divide into 3
- Units change to Unit

EAM follow-up edit
- Tested & Passed

EAM follow-up view
- css for Part A disappeared
- Part B Not display Numbering for question

EAM follow-up view
Click on Print icon page return "THE SYSTEM HAS ENCOUNTERED AN ERROR. PLEASE CONTACT SYSTEM ADMINISTRATOR."

To remove Product & Service text field at Potential to be one only.

#5 Updated by Najmi Pasarudin over 7 years ago

  • Status changed from Development / Work In Progress to Internal Testing
  • Assignee changed from Najmi Pasarudin to Siti Norahayu Mohd Desa
  • % Done changed from 60 to 90

Please test:

# TF follow-up view
# TF follow-up print/empty
# EAM follow-up view
# EAM follow-up print/empty

#6 Updated by Siti Norahayu Mohd Desa over 7 years ago

  • Status changed from Internal Testing to Work Completed-End life cycle
  • % Done changed from 90 to 100

Tested & Passed.

Also available in: Atom PDF