[UAT_RIB001] - Takaful Purchase - Own Account
Status: | Work Completed-End life cycle | Start date: | March 06, 2017 | |
---|---|---|---|---|
Priority: | Normal | Due date: | March 06, 2017 | |
Assignee: | Norhaidah Md Dasuki | % Done: | 100% | |
Category: | RIB | Spent time: | - | |
Target version: | - |
Description
Issue:
Unable to purchase takaful. Occupation cannot be edited due too it read from DB and the value is null.
This is based on requirement in URS which is:-
o If IB User click Own Account, IB system will auto default all the above data (maintainable).
Resolution:
Based on discussion and confirm by User, please fix the input screen as per below:
1. Only Name and New NRIC No field - Not Editable
2. Others Field - Editable
*Refer attached image
Related issues
History
#1 Updated by Stephanie Sufrapto over 7 years ago
- Status changed from New - Begin Life Cycle to Development / Work In Progress
- % Done changed from 0 to 100
#2 Updated by Stephanie Sufrapto over 7 years ago
- Status changed from Development / Work In Progress to Internal Testing
- Assignee changed from Stephanie Sufrapto to Erni Suhaireen Zulkifli
Hi Erni,
Please retest on SIT first. If ok will deployed to UAT
#3 Updated by Stephanie Sufrapto over 7 years ago
- Assignee changed from Erni Suhaireen Zulkifli to Siti Norahayu Mohd Desa
#4 Updated by Stephanie Sufrapto over 7 years ago
Add: Numeric validation for Postcode
#5 Updated by Norhaidah Md Dasuki over 7 years ago
- Due date set to March 06, 2017
- Assignee changed from Siti Norahayu Mohd Desa to Erni Suhaireen Zulkifli
- Start date changed from March 02, 2017 to March 06, 2017
- % Done changed from 100 to 80
Erni, Kindly assist to test.
#6 Updated by Erni Suhaireen Zulkifli over 7 years ago
- Status changed from Internal Testing to Work Completed-End life cycle
- % Done changed from 80 to 100
Tested and Pass
#7 Updated by Erni Suhaireen Zulkifli over 7 years ago
- Status changed from Work Completed-End life cycle to Pending Review
- Assignee changed from Erni Suhaireen Zulkifli to Norhaidah Md Dasuki
#8 Updated by Norhaidah Md Dasuki over 7 years ago
- Status changed from Pending Review to User Acceptance Test
8/3/2017 - Send for SIT/UAt
#9 Updated by Norhaidah Md Dasuki over 7 years ago
- Status changed from User Acceptance Test to Pending UAT Deployment
#10 Updated by Norhaidah Md Dasuki over 7 years ago
- Status changed from Pending UAT Deployment to User Acceptance Test
#11 Updated by Norhaidah Md Dasuki over 7 years ago
- Status changed from User Acceptance Test to Work Completed-End life cycle
Successfully tested by user. Plan to migrate to production by 16/6/17.