Bug #7226

Task #7184: TPMS CR201702 - Post-Event report

[TPMS CR201702] - Event Report > Trade Fair > Total Sales by Events

Added by Siti Norahayu Mohd Desa over 7 years ago. Updated over 7 years ago.

Status:Work Completed-End life cycleStart date:March 06, 2017
Priority:UrgentDue date:March 06, 2017
Assignee:Siti Norahayu Mohd Desa % Done:

100%

Category:TPMS_TestSpent time:-
Target version:-

Description

1. Total Amount for Potential Sales not Tally
2. Alter the highlighted box to standardize the Sales Generated.
3. Remove RM at Sales Generated row.

Please refer attached.

Total sales by Events.png (110 KB) Siti Norahayu Mohd Desa , March 06, 2017 14:56

History

#1 Updated by Siti Norahayu Mohd Desa over 7 years ago

  • Assignee changed from Siti Norahayu Mohd Desa to Tan Jeng Wei

#2 Updated by Siti Norahayu Mohd Desa over 7 years ago

  • Description updated (diff)

#3 Updated by Tan Jeng Wei over 7 years ago

  • % Done changed from 0 to 100

#4 Updated by Tan Jeng Wei over 7 years ago

  • Assignee changed from Tan Jeng Wei to Siti Norahayu Mohd Desa

Hi ayu,

1. Total Amount for Potential Sales not Tally --> Fixed
2. Alter the highlighted box to standardize the Sales Generated.--> Fixed
3. Remove RM at Sales Generated row.--> Fixed

#5 Updated by Siti Norahayu Mohd Desa over 7 years ago

  • Status changed from New - Begin Life Cycle to Development / Work In Progress
  • Assignee changed from Siti Norahayu Mohd Desa to Tan Jeng Wei
  • % Done changed from 100 to 90

UNABLE TO OPEN THE REPORT.

#6 Updated by Tan Jeng Wei over 7 years ago

  • Status changed from Development / Work In Progress to Internal Testing
  • Assignee changed from Tan Jeng Wei to Siti Norahayu Mohd Desa

#7 Updated by Siti Norahayu Mohd Desa over 7 years ago

  • Status changed from Internal Testing to Work Completed-End life cycle
  • % Done changed from 90 to 100

Tested & Passed.

Additional:
1. Change Midterm to Mid Term
2. Re-order Actual Sales (%) to be center

#8 Updated by Siti Norahayu Mohd Desa over 7 years ago

  • Status changed from Work Completed-End life cycle to Development / Work In Progress
  • Assignee changed from Siti Norahayu Mohd Desa to Tan Jeng Wei
  • % Done changed from 100 to 90

#9 Updated by Tan Jeng Wei over 7 years ago

  • Status changed from Development / Work In Progress to Internal Testing
  • Assignee changed from Tan Jeng Wei to Siti Norahayu Mohd Desa
  • % Done changed from 90 to 100

Hi ayu,

Additional:
1. Change Midterm to Mid Term --> Fixed
2. Re-order Actual Sales (%) to be center --> Fixed

will deploy around 12pm.

#10 Updated by Siti Norahayu Mohd Desa over 7 years ago

  • Status changed from Internal Testing to Development / Work In Progress
  • Assignee changed from Siti Norahayu Mohd Desa to Tan Jeng Wei
  • Priority changed from Normal to Urgent

Potential Sale display wrong value.

Actual Result:
ADTEK MARKETING SDN BHD
Short Term - RM 133,350.05
Mid Term - RM 10,000.00
Long Term - RM 10,000.00
TOTAL = RM 153,350.05

Expecting Result:
ADTEK MARKETING SDN BHD
Short Term - RM44450.04
Mid Term - RM44450.00
Long Term - 44450.00
TOTAL = RM 133,350.05

#11 Updated by Tan Jeng Wei over 7 years ago

  • Status changed from Development / Work In Progress to Internal Testing
  • Assignee changed from Tan Jeng Wei to Siti Norahayu Mohd Desa

#12 Updated by Siti Norahayu Mohd Desa over 7 years ago

  • Status changed from Internal Testing to Work Completed-End life cycle

Tested & Passed.