Support #8837
SCP ID :##4733##] : 4771##] : RMBP - TAC Requirement MSS
Status: | Dropped-End of life cycle | Start date: | October 26, 2018 | |
---|---|---|---|---|
Priority: | Normal | Due date: | October 26, 2018 | |
Assignee: | Rayvandy Gabbytian | % Done: | 100% | |
Category: | - | Spent time: | - | |
Target version: | - |
Description
Hi,
Kindly attend below request:
RMBP validation problem on transaction submission (last step) when TAC requirement were set to "No" on MSS.
History
#1 Updated by Zahir Abd Latif almost 6 years ago
- Project changed from Agrobank Support to Maybank BII M2U-RIB Support
- Category deleted (
RIB) - Assignee changed from Stephanie Sufrapto to Rayvandy Gabbytian
#2 Updated by Rayvandy Gabbytian almost 6 years ago
- Due date set to October 26, 2018
- Status changed from New - Begin Life Cycle to Development / Work In Progress
- Assignee changed from Rayvandy Gabbytian to Aditya Prathama
Dear Adit,
You have delivered this patch on Friday 26th October 2018 and passed testing. Kindly update the redmine status.
Thank you.
#3 Updated by Aditya Prathama almost 6 years ago
- Status changed from Development / Work In Progress to Finished Development
- Assignee changed from Aditya Prathama to Rayvandy Gabbytian
update the status. thanks for the remainder
#4 Updated by Rayvandy Gabbytian over 5 years ago
This case is Pending for APK deployment and having problem with IPA due to obsolete IDE (Xcode).
#5 Updated by Rayvandy Gabbytian about 5 years ago
- Status changed from Finished Development to Development / Work In Progress
- % Done changed from 0 to 100
Unable to proceed this fixes into production, because:
- need to rewrite the code (sencha upgrade),
- need to upgrade worklight to mobile first,
- need to upgrade xcode.
#6 Updated by Rayvandy Gabbytian about 5 years ago
- Status changed from Development / Work In Progress to Dropped-End of life cycle