Change #9725
Logout page does not have last activity summary
Status: | Work Completed-End life cycle | Start date: | March 14, 2019 | |
---|---|---|---|---|
Priority: | Normal | Due date: | March 15, 2019 | |
Assignee: | - | % Done: | 100% | |
Category: | - | Spent time: | - | |
Target version: | - |
Description
Feature: Logout page does not have last activity summary
User ID: penrilinit2
User Role: Initiator
Step to Reproduce:
1. Go to CDB Login > logout
Current Result:
System is not displaying the logout summary.
Expected Result:
System should display the logout summary.
History
#1 Updated by Siti Norahayu Mohd Desa over 5 years ago
- Assignee changed from Nur Hazirah Mohd Razali to Najmi Pasarudin
#2 Updated by Najmi Pasarudin over 5 years ago
- Status changed from New - Begin Life Cycle to Development / Work In Progress
#3 Updated by Najmi Pasarudin over 5 years ago
- % Done changed from 0 to 50
Feature is working. Pending updating the details.
#4 Updated by Najmi Pasarudin over 5 years ago
- Status changed from Development / Work In Progress to Internal Testing
- Assignee changed from Najmi Pasarudin to Siti Norahayu Mohd Desa
- % Done changed from 50 to 90
Please test after 07/03/2019 6.30pm deployment.
Feature added:
- Logout summary - Please verify summary details
- Save as PDF button - Please verify PDF logout summary
#5 Updated by Anonymous over 5 years ago
- Tracker changed from Feature to Change
- Due date changed from March 05, 2019 to March 15, 2019
- Status changed from Internal Testing to Development / Work In Progress
- Assignee changed from Siti Norahayu Mohd Desa to Najmi Pasarudin
- Start date changed from March 05, 2019 to March 14, 2019
- % Done changed from 90 to 80
Hi Najmi,
kindly changes the listing order to be descending. (Latest action at top)
Current : System display in ascending order.
#6 Updated by Najmi Pasarudin over 5 years ago
- Status changed from Development / Work In Progress to Internal Testing
- Assignee changed from Najmi Pasarudin to Anonymous
- % Done changed from 80 to 90
Please retest after 14/03/2019 6pm deployment.
#7 Updated by Anonymous about 5 years ago
- Status changed from Internal Testing to Work Completed-End life cycle
- % Done changed from 90 to 100