Task #975
AGROINFRA: PROD Network Installation
Status: | Work Completed-End life cycle | Start date: | June 20, 2011 | |
---|---|---|---|---|
Priority: | Normal | Due date: | June 30, 2011 | |
Assignee: | Abu Bakar Mohamed Sahabanali | % Done: | 100% | |
Category: | - | Spent time: | - | |
Target version: | - |
Description
Follow up on the network installation status on the Production site
History
#1 Updated by Ahmad Hazri about 13 years ago
- Assignee changed from Ahmad Hazri to Abu Bakar Mohamed Sahabanali
#2 Updated by Abu Bakar Mohamed Sahabanali about 13 years ago
- Status changed from New - Begin Life Cycle to Work Completed-End life cycle
- % Done changed from 0 to 100
PROD network installation done on 26/06/2011