Task #977
AGROINFRA: PROD Network UAT
Status: | Work Completed-End life cycle | Start date: | June 27, 2011 | |
---|---|---|---|---|
Priority: | Normal | Due date: | July 08, 2011 | |
Assignee: | Abu Bakar Mohamed Sahabanali | % Done: | 100% | |
Category: | - | Estimated time: | 1.00 hour | |
Target version: | - | Spent time: | - |
Description
To perform and monitor Production site network connection UAT until signoff
History
#1 Updated by Ahmad Hazri about 13 years ago
- Assignee changed from Ahmad Hazri to Abu Bakar Mohamed Sahabanali
#2 Updated by Abu Bakar Mohamed Sahabanali about 13 years ago
- Status changed from New - Begin Life Cycle to Work Completed-End life cycle
- % Done changed from 0 to 100
- Estimated time set to 1.00
PROD network UAT done on 28/06/2011