September 21, 2021
- 14:46 Support #12337 (Pending Prod Deployment): [SCP ID :##5980##] : Exceed Company Daily Limit
- Issue : BIB includes SI delele inside company daily limit calculation.
Solution : we will exclude SI delete from C...
September 18, 2021
- 09:59 Support #12343 (Work Completed-End life cycle): [SCP ID :##5984##] : FPX - session expired
- Hi,
Kindly attend below request:
Customer experience session expired once click confirm button when perform FPX t... - 09:55 Support #12342 (Work Completed-End life cycle): [SCP ID :##5983##] : FPX - not received TAC
- Hi,
Kindly attend below request:
Hi Team,
I am not receive TAC when perform fpx transaction. Recently we ...
September 15, 2021
- 12:49 Support #12337 (Pending Prod Deployment): [SCP ID :##5980##] : Exceed Company Daily Limit
- Hi,
Kindly attend below request:-
BIB customer unable to perform maintenance DuitNow (delete SI) with error excee...
September 13, 2021
- 09:56 Support #12326 (Work Completed-End life cycle): [SCP ID :##5977##] : ISS report issue
- We suspect issue is caused by JRXML use to export the excel.
Solution:We change the to using file to padding csv whi...
September 10, 2021
- 10:29 Support #12326 (Work Completed-End life cycle): [SCP ID :##5977##] : ISS report issue
- Hi,
Kindly attend below request:-
FYI, ISS report for august 2021 was not successfully generated. I try generate...
September 09, 2021