October 23, 2012
- 11:29 Task #1651 (Work Completed-End life cycle): Resources Bundle Translation
- This task is closed and will be test during the next project implementation
October 11, 2012
- 14:37 Task #1651: Resources Bundle Translation
- Hi Lee Yong,
Kindly refer to the excel file and assist to do final review on the Malay Translation for Agrobank Mu... - 14:27 Task #1651: Resources Bundle Translation
- please assit assign to Lee Yong after completed since no customer/user will be involved from Agrobank at this moment.
- 10:17 Task #1651 (Pending Review): Resources Bundle Translation