Activity
From October 08, 2010 to November 06, 2010
November 04, 2010
- 09:10 Task #596 (Work Completed-End life cycle): IBFT User Limit
- update status
- 09:09 Task #596: IBFT User Limit
- Tested by hafiz
Status : passed
November 03, 2010
- 20:10 Task #593: IBFT Transfer (Open & Registered)
- tested: TAC, result page
todo: test limit, test SMS, test mock data prepared by vince - 18:53 Task #599 (Work Completed-End life cycle): Test Script for IBFT
- Change status.
Assigned to latipah - 18:51 Task #599: Test Script for IBFT
- This Test Script is base of BRS
- 18:24 Task #596 (Internal Testing): IBFT User Limit
- Add user limit for IBFT at Transfer Limit module:
* Open IBFT Transfer
* Registered IBFT Transfer
~~ Don... - 18:15 Task #604 (Work Completed-End life cycle): IBFT: SAN Report Retrieval
- Development done. Need to test with actualy SAN Rerport.
November 02, 2010
- 14:04 Task #604 (Development / Work In Progress): IBFT: SAN Report Retrieval
- 10:22 Task #604 (Work Completed-End life cycle): IBFT: SAN Report Retrieval
- To develop a SAN report download feature in CORUS
- 10:17 Task #603 (Dropped-End of life cycle): IBFT Mock up
- To create a mock up for IBFT project.
November 01, 2010
- 13:45 Task #599: Test Script for IBFT
- The latest BRS v1.0 is available at http://hub.penril.net/redmine/attachments/427/IBFT-_BRS_V1.0.pdf or can click at ...
- 13:22 Document: BRS for IBFT
- 10:32 Task #596 (Development / Work In Progress): IBFT User Limit
- Add user limit for IBFT at Transfer Limit module:
* Open IBFT Transfer
* Registered IBFT Transfer
- co...
October 29, 2010
- 19:57 Task #591: IBFT Fav Maintenance (Enquiry,Add,Edit,Del)
- add, edit and delete fully function but without esb integration.
- 11:43 Task #544 (Work Completed-End life cycle): IBFT: Compile BRS
- Delay due to more time spend at other task: IBG 2nd validation UAT at KFH.
October 28, 2010
- 21:10 Task #593: IBFT Transfer (Open & Registered)
- todo:
- apply sms function
- test transfer limit
- haven't fully test until result page - 19:17 Task #591: IBFT Fav Maintenance (Enquiry,Add,Edit,Del)
- 1.interface - done
2.action - done
3.service - done
4.service info integration - done
4.add into table when user ...
October 27, 2010
- 18:11 Task #600 (Work Completed-End life cycle): Migration Plan for IBFT
- Prepare the PRODUCTION migration plan, scripts and files including table schema, BVMC related, class files, resource ...
- 17:43 Task #599 (Work Completed-End life cycle): Test Script for IBFT
- Prepare test script for IBFT based on BRS.
- 17:37 Task #544 (Development / Work In Progress): IBFT: Compile BRS
- After complete, please forward to Hafiz for him to do the test script.
- 16:19 Task #592 (Development / Work In Progress): IBFT Reports
- Done creating & updating reports related to IBFT but cannot be fully tested coz IB part for IBFT Transfer module is n...
- 13:28 Task #596 (Work Completed-End life cycle): IBFT User Limit
- Add user limit for IBFT at Transfer Limit module:
* Open IBFT Transfer
* Registered IBFT Transfer - 12:39 Task #589 (Work Completed-End life cycle): BVMC Settings and Parameters
- BVMC
• *Service configuration (IBFTOPEN,IBFTFAV,IBFTEDIT,IBFTADD,IBFTDEL*) - created at IB Service Info content
â... - 09:16 Task #594 (Work Completed-End life cycle): Integration with oc4j
- ESB Services for IBFT Function : Account Enquiry & Fund Transfer has been done and tested.
October 26, 2010
- 18:14 Task #591: IBFT Fav Maintenance (Enquiry,Add,Edit,Del)
- * Favourite accounts are stored into BVMC extended table IB_IBFT_ACCOUNTS already created by Darsy
- 18:10 Task #593: IBFT Transfer (Open & Registered)
- Added:
Sequence: *IBFT_TRANSFER_SEQ*... - 17:09 Task #594 (Closed - End of life cycle): Integration with oc4j
- Create method/service for IBFT back-end
- 17:03 Task #593 (Work Completed-End life cycle): IBFT Transfer (Open & Registered)
- use these service info:
IBFTOPEN - open trnx, daily open IBFT bank limit
IBFTFAV - fav trnx, daily fav IBFT bank li... - 15:54 Task #592 (Work Completed-End life cycle): IBFT Reports
- New report:
# IBFT report
Report modification:
# internet transaction history report
# daily consolidated repor... - 15:48 Task #591 (Work Completed-End life cycle): IBFT Fav Maintenance (Enquiry,Add,Edit,Del)
- Use these service info:
IBFTEDIT - notes n tac for Edit maintenance
IBFTADD - notes n tac for Add maintenance
IBFT... - 15:32 Task #589 (Work Completed-End life cycle): BVMC Settings and Parameters
- BVMC
• Service configuration (IBFTOPEN,IBFTFAV,IBFTEDIT,IBFTADD,IBFTDEL)
• HPS/MEPS IBFT member banks’ detail...
October 21, 2010
- 23:00 Task #544 (Work Completed-End life cycle): IBFT: Compile BRS
- IBFT BRS completed. Reviewed by Jelson and need some changes.
- 22:56 Task #543 (Work Completed-End life cycle): IBFT: SIT
- Complete test on the IBFT Functions:
1. Account Enquiry
2. Fund Transfer
Further test required When IBFT...
October 14, 2010
- 15:49 Task #543: IBFT: SIT
- Tested both Account Enquiry & Fund Transaction functions and it returns good response. Will test again tomorrow to ma...
- 14:13 Task #544 (Work Completed-End life cycle): IBFT: Compile BRS
- To compile the BRS for the scope state below:-
1. Consumer Internet Banking
• IBFT Transfer
• Favorite Ma... - 13:52 Task #543: IBFT: SIT
- Integration with OC4J
- 13:49 Task #543 (Closed - End of life cycle): IBFT: SIT
- Doing system integration implementation and testing with HPS personnel, Sara and Chakour
Also available in: Atom