16:11 eDividend Task #488: Testing eDividend Module
- done test script
- further test for fixing bug
Hafizudin MD

October 08, 2010

17:35 eDividend Task #480: Development for eDividend
# Re-designing eDividend to reuse existing coding better
# In the process of merging with Production and EPF BIB pro...
Wong Bernard

October 07, 2010

17:33 CORUS Secured Mailbox Task #263: Subject Maintenance
working on subject maintenance using latest database design Nor Shuhaida Subri
17:03 eDividend Task #503 (Work Completed-End life cycle): CORUS changes for eDividend (Charges related)
# Can successfully view, update and approve eDividend charges.
# Require future testing
Wong Bernard

October 05, 2010

17:08 eDividend Task #506: Updating BRS Document
# Match BRS document with current development and bug fixes changes (mostly screenshots)
# Code changes to match scre...
Wong Bernard
17:06 eDividend Task #506 (Dropped-End of life cycle): Updating BRS Document
Wong Bernard

October 04, 2010

16:54 eDividend Task #503 (Work Completed-End life cycle): CORUS changes for eDividend (Charges related)
Wong Bernard
16:28 eDividend Bug #502: Reports for eDividends
# Fixed no reports being downloaded for Bulk Payment
# Separated Bulk Payment Open/Payroll from rest of other servic...
Wong Bernard
16:24 eDividend Bug #502 (New - Begin Life Cycle): Reports for eDividends
Wong Bernard

September 30, 2010

02:41 CORUS Secured Mailbox Task #498 (New - Begin Life Cycle): CORUS MessageBox User Guide
Tan Lee Yong
02:39 CIB Secured Mailbox Task #497 (New - Begin Life Cycle): CIB MessageBox User Guide
Tan Lee Yong
02:37 BIB Secured Mailbox Task #496 (New - Begin Life Cycle): BIB MessageBox User Guide
Tan Lee Yong
16:18 eDividend Task #488: Testing eDividend Module
Bernard has completed the first 10% of work.
Reassign to Hafiz to continue testing.
1) Create test script
2) Revie...
Tan Lee Yong
13:32 CIB Secured Mailbox Task #312: Prepare UAT Test Script for CIB Secured Mailbox
testscript for cib secure mailbox v3 Hafizudin MD
13:05 eDividend Task #488 (Dropped-End of life cycle): Testing eDividend Module
Wong Bernard
13:04 eDividend Task #480 (Work Completed-End life cycle): Development for eDividend
# Successfully uploaded sample eDividend batch file and saved to database.
# Require more extensive testing
Wong Bernard

September 29, 2010

12:34 eDividend Task #480: Development for eDividend
# Reports completed
# Testing uploading sample eDividend file. Running into inconsistency with BRS file upload spec...
Wong Bernard

September 24, 2010

17:15 KFH Secured Mailbox Task #447: Updating BRS
How is the progress on this BRS? Tan Lee Yong
17:05 Task #482 (Closed - End of life cycle): Rentas Notification email error - HD00009390
Tan Lee Yong
12:19 Task #482: Rentas Notification email error - HD00009390
Correction. The user is confused whether the email is generated from production or staging server, not refuses.
Just...
Tan Lee Yong
12:12 Task #482: Rentas Notification email error - HD00009390
Yes, the email message is configurable through properties file. But he actually forgotten that he not supposed to get... Sarinah Darsy
12:09 Task #482 (Work Completed-End life cycle): Rentas Notification email error - HD00009390
He is refuses whether the email is generated from production or staging server. That email act is generated from stag... Sarinah Darsy
12:01 Task #482 (Closed - End of life cycle): Rentas Notification email error - HD00009390
Kamaruddin reported:-
Rentas Notification email:
1) No email receive for today at 10am (24/09/10)
2) Date Differ...
Tan Lee Yong
11:55 Task #410 (User Acceptance Test): C007 - Bulk Payment Search Result Page
Latipah, take this task on until migrated to production. Tan Lee Yong

September 21, 2010

17:29 eDividend Task #480: Development for eDividend
# Coding for accepting eDividend upload file almost completed
# Coding for report generation and testing will follow
Wong Bernard
17:27 eDividend Task #480 (Work Completed-End life cycle): Development for eDividend
Wong Bernard

September 17, 2010

18:16 CORUS Secured Mailbox Task #263: Subject Maintenance
pagination done.
postpone due to newest database design by cheeping complete.
Nor Shuhaida Subri

September 15, 2010

17:14 Task #410 (Work Completed-End life cycle): C007 - Bulk Payment Search Result Page
Fixed.
Either comment out the whole EPF parts for a quick fix or wait for the EPF modules to be deployed and it wi...
Ang Wei Cheng
15:59 Task #410 (Pending Customer Feedback): C007 - Bulk Payment Search Result Page
It was caused by the partial removal of EPF module. Some of the EPF columns is still defined in the BIB Reports colum... Ang Wei Cheng
12:42 Task #410 (Development / Work In Progress): C007 - Bulk Payment Search Result Page
No error in BIB epf branch.
Able to reproduce the error in BIB stable.
Still try to figure out what went wrong. Lack ...
Ang Wei Cheng

September 14, 2010

18:06 CORUS Secured Mailbox Task #263: Subject Maintenance
There are 3 listing page inside Subject Maintenance
1. Listing all subject - done
2. Listing all user - done
3. Li...
Nor Shuhaida Subri

September 13, 2010

18:06 CIB Secured Mailbox Task #403 (Closed - End of life cycle): Update CIB SecuredMailbox BRS v1.0
Tan Lee Yong
18:05 CORUS Secured Mailbox Task #355 (Closed - End of life cycle): Update CORUS Subject Maintenance BRS
Tan Lee Yong
18:05 CORUS Secured Mailbox Task #98 (Closed - End of life cycle): CORUS Sent Box Read Message
Tan Lee Yong
18:04 CORUS Secured Mailbox Task #95 (Closed - End of life cycle): CORUS Inbox Read Message
Tan Lee Yong
18:03 CORUS Secured Mailbox Task #93 (Closed - End of life cycle): CORUS mailbox listing
Tan Lee Yong
18:02 BIB Secured Mailbox Task #311 (Closed - End of life cycle): Prepare UAT Test Script for BIB Secured Mailbox
Tan Lee Yong
18:02 BIB Secured Mailbox Task #402 (Closed - End of life cycle): Update BIB SecuredMailbox BRS v1.0
Tan Lee Yong
18:02 CORUS Secured Mailbox Task #263: Subject Maintenance
- to deploy new table and set new instance for corus secure mailbox inside demo server 3
- continue working on pagin...
Nor Shuhaida Subri
18:02 BIB Secured Mailbox Task #63 (Closed - End of life cycle): BIB Secured Mailbox Validation
Tan Lee Yong
18:01 BIB Secured Mailbox Task #61 (Closed - End of life cycle): BIB Trash box Action
Tan Lee Yong
18:01 BIB Secured Mailbox Task #60 (Closed - End of life cycle): BIB Sent Box Action
Tan Lee Yong
18:00 BIB Secured Mailbox Task #59 (Closed - End of life cycle): BIB Inbox Reply Action
Tan Lee Yong
18:00 BIB Secured Mailbox Task #58 (Closed - End of life cycle): BIB Inbox Action
Tan Lee Yong
17:55 CORUS Secured Mailbox Task #263: Subject Maintenance
Please update the status and the planned due date Tan Lee Yong
17:54 CORUS Secured Mailbox Task #404 (Closed - End of life cycle): Update CORUS SecuredMailbox BRS v1.0
Tan Lee Yong
17:25 eDividend Follow Up #411: BRS Discussion v1.0
Has been submitted the latest document, KFH BRS-eDividend v1.2 20100902.docx, to stakeholder.
The latest doc is chec...
Tan Lee Yong
 