- 11:50 KFH Secured Mailbox Task #447: Updating BRS
- # No progress as changes made have not been implemented. Only when fully implement can the BRS be updated (especiall...
October 22, 2010
- 18:35 CORUS Secured Mailbox Task #263: Subject Maintenance
- working on delete user inside specific subject.
October 18, 2010
- 16:52 eDividend Bug #502: Reports for eDividends
- # Updated new design to have reports
# Require more testing and cover Hafiz findings
October 12, 2010
- 16:11 eDividend Task #488: Testing eDividend Module
- - done test script
- further test for fixing bug
October 08, 2010
- 17:35 eDividend Task #480: Development for eDividend
- # Re-designing eDividend to reuse existing coding better
# In the process of merging with Production and EPF BIB pro...
October 07, 2010
- 17:33 CORUS Secured Mailbox Task #263: Subject Maintenance
- working on subject maintenance using latest database design
- 17:03 eDividend Task #503 (Work Completed-End life cycle): CORUS changes for eDividend (Charges related)
- # Can successfully view, update and approve eDividend charges.
# Require future testing
October 05, 2010
- 17:08 eDividend Task #506: Updating BRS Document
- # Match BRS document with current development and bug fixes changes (mostly screenshots)
# Code changes to match scre... - 17:06 eDividend Task #506 (Dropped-End of life cycle): Updating BRS Document
October 04, 2010
- 16:54 eDividend Task #503 (Work Completed-End life cycle): CORUS changes for eDividend (Charges related)
- 16:28 eDividend Bug #502: Reports for eDividends
- # Fixed no reports being downloaded for Bulk Payment
# Separated Bulk Payment Open/Payroll from rest of other servic... - 16:24 eDividend Bug #502 (New - Begin Life Cycle): Reports for eDividends
September 30, 2010
- 02:41 CORUS Secured Mailbox Task #498 (New - Begin Life Cycle): CORUS MessageBox User Guide
- 02:39 CIB Secured Mailbox Task #497 (New - Begin Life Cycle): CIB MessageBox User Guide
- 02:37 BIB Secured Mailbox Task #496 (New - Begin Life Cycle): BIB MessageBox User Guide
- 16:18 eDividend Task #488: Testing eDividend Module
- Bernard has completed the first 10% of work.
Reassign to Hafiz to continue testing.
1) Create test script
2) Revie... - 13:32 CIB Secured Mailbox Task #312: Prepare UAT Test Script for CIB Secured Mailbox
- testscript for cib secure mailbox v3
- 13:05 eDividend Task #488 (Dropped-End of life cycle): Testing eDividend Module
- 13:04 eDividend Task #480 (Work Completed-End life cycle): Development for eDividend
- # Successfully uploaded sample eDividend batch file and saved to database.
# Require more extensive testing
September 29, 2010
- 12:34 eDividend Task #480: Development for eDividend
- # Reports completed
# Testing uploading sample eDividend file. Running into inconsistency with BRS file upload spec...