July 23, 2010

Avatar?id=1733&size=24 12:45 Task #168 (Development / Work In Progress): DR Setup
Updated by Adam (KFH) the PaySwitch PC will move to Kompakar tentatively on July 30, 2010.
Will continue for the fin...
Ahmad Hazri
11:24 Task #168: DR Setup
Please update the due date and/or status Tan Lee Yong

July 01, 2010

Avatar?id=1733&size=24 11:50 Task #168: DR Setup
1)Mounting to PaySwitch server is fine.
2)Arranging with KFH IT to move the IBG machine to Kompakar
Final steps...
Ahmad Hazri

June 30, 2010

Avatar?id=1733&size=24 19:13 Task #168: DR Setup
Status:
Jboss - installed
Oracle client - installed
Unison - installed
mapping/sharing to payswitch client - te...
Ahmad Hazri

June 29, 2010

Avatar?id=1733&size=24 17:40 Task #168 (Work Completed-End life cycle): DR Setup
KFHIB - IBGCore DR server Preparation
Application List
====================
Oracle Client
Samba Client
JBoss A...
Ahmad Hazri
 