Task #168
DR Setup
Status: | Work Completed-End life cycle | Start date: | June 29, 2010 | |
---|---|---|---|---|
Priority: | High | Due date: | August 03, 2010 | |
Assignee: | Ahmad Hazri | % Done: | 100% | |
Category: | - | Estimated time: | 3.00 hours | |
Target version: | - | Spent time: | 3.00 hours |
Description
KFHIB - IBGCore DR server Preparation
Application List
====================
Oracle Client
Samba Client
JBoss AS
Unison synchronizer
Mapping/sharing
====================
IBGCore ---> IB AS
> Unison synchronizer
> SSH Passwordless
IBGCore ---> PaySwitch
>Samba client
Port list
==========
JBoss -- 4242 -- Incoming
Oracle -- 1088 -- Outgoing
ESB -- 7003 -- Outgoing
Samba (win) -- 445 -- Outgoing
Server related list
====================
[DR]
KFHIB19 -- IBGCore
KFHIB14 -- IB AS
KFHIB15 -- ESB server
KFHIB16 -- Oracle DB
[PRODUCTION]
KFHIB18 -- IBGCOre
KFHIB03/04 -- IB AS
KFHIB05 -- ESB Server
KFHIB07 -- Oracle DB
History
#1 Updated by Ahmad Hazri about 14 years ago
- % Done changed from 30 to 40
Status:
Jboss - installed
Oracle client - installed
Unison - installed
mapping/sharing to payswitch client - testing & working. will set permanently once moved to Kompakar
synchronizer script - created
#2 Updated by Ahmad Hazri about 14 years ago
- % Done changed from 40 to 60
1)Mounting to PaySwitch server is fine.
2)Arranging with KFH IT to move the IBG machine to Kompakar
Final steps in Kompakar
1) Mounting with Payswitch DR IP 2) SSH passwordless connection from IBGCOre to IB server
#3 Updated by Tan Lee Yong about 14 years ago
Please update the due date and/or status
#4 Updated by Ahmad Hazri about 14 years ago
- Due date set to August 03, 2010
- Status changed from New - Begin Life Cycle to Development / Work In Progress
Updated by Adam (KFH) the PaySwitch PC will move to Kompakar tentatively on July 30, 2010.
Will continue for the final steps on August 3, 2010 once the PaySwitch moved.
#5 Updated by Ahmad Hazri about 14 years ago
- Status changed from Development / Work In Progress to Pending Customer Feedback
Pending on Adam (KFH) to moving the PaySwich PC to Kompakar site.
No date confirm.
#6 Updated by Tan Lee Yong almost 14 years ago
What is the status on this?
#7 Updated by Tan Lee Yong almost 14 years ago
Need status
#8 Updated by Ahmad Hazri almost 14 years ago
- Status changed from Pending Customer Feedback to Work Completed-End life cycle
- % Done changed from 60 to 100
- Estimated time set to 3.00
Understood from Rosli, there is no PaySwitch PC for DR, means all data transfer will does manually by Adham (KFH).
Hence, this task considered resolved.