15:16 IBSCR012-IBGCore for GFS Task #246 (Development / Work In Progress): UAT Monitoring
UAT to be completed by this Friday. Will prepare a UAT sign off form for KFH. Low Jelson

August 11, 2010

10:21 Revision 349:c9f8697378c2: include J.P. Morgan Chase Bank in Interbank List
Vincent Devethas

August 09, 2010

Avatar?id=1733&size=24 14:24 DR-IBGCore Task #168 (Pending Customer Feedback): DR Setup
Pending on Adam (KFH) to moving the PaySwich PC to Kompakar site.
No date confirm.
Ahmad Hazri

July 30, 2010

12:18 IBSCR012-IBGCore for GFS Task #247 (Closed - End of life cycle): Migration Plan for IBGCore for GFS
IBG patches ready for Production migration (version 3):
> IBGWS.war
> scheduler.war
> IBGCore
Note: will updat...
Vincent Devethas
12:06 IBSCR012-IBGCore for GFS Task #248 (Work Completed-End life cycle): Update IBGCore Documentation
changes to the IBG entry via Branch. Vincent Devethas

July 28, 2010

17:55 IBSCR012-IBGCore for GFS Task #248 (Development / Work In Progress): Update IBGCore Documentation
Vincent Devethas
17:54 IBSCR012-IBGCore for GFS Task #247 (Development / Work In Progress): Migration Plan for IBGCore for GFS