October 14, 2010
- 16:26 IBG Second Validation Task #546 (Work Completed-End life cycle): Fund Transfer Limit
- 1. Fund transfer limit increased from 100,000 to 500,000. So that KFH Account holders able to transfer an amount up t...
- 16:21 IBG Second Validation Task #545 (Work Completed-End life cycle): IBGCore to Perform 2nd Validation
- OFI NACHA File:
1. Reserved field defaulted to "0", means no validation.
2. Relocate segment code to the reserved f...
October 09, 2010
- 00:48 DR-IBGCore Task #168 (Work Completed-End life cycle): DR Setup
- Understood from Rosli, there is no PaySwitch PC for DR, means all data transfer will does manually by Adham (KFH).
H...
October 07, 2010
- 14:42 DR-IBGCore Task #168: DR Setup
- Need status
September 24, 2010
- 17:22 DR-IBGCore Task #168: DR Setup
- What is the status on this?
- 17:21 Task #449 (Closed - End of life cycle): MEPS IBG - AGRO Participation
- Go production on 20/09/2010