Activity
From June 01, 2010 to June 30, 2010
June 30, 2010
- 16:48 Task #180: Test Script for report
- New Update.
- 16:14 Task #180: Test Script for report
- New update for Testscript SMS Notification.
- 12:53 Task #180: Test Script for report
- Wrong update.
- 12:38 Task #180 (Work Completed-End life cycle): Test Script for report
- Include Testscript, will verify the Demand Draft and Banker's Cheque Report fields.
June 29, 2010
- 18:31 Task #182 (Closed - End of life cycle): Internal Test for report
- Perform internal test for SMS Report, TAC report and Consolidated report for monthly and daily.
- 18:28 Task #180 (Closed - End of life cycle): Test Script for report
- Please create test script for the report. See the report format from the BRS.
- 18:27 Task #179 (Closed - End of life cycle): Code Review
- Code review for IBUtils
- 18:24 Task #178 (Closed - End of life cycle): Code Review
- Code Review. For any issue, please open a new issue for the stakeholder to fix the problem and have QA to test it.
- 13:24 Task #82: Testing SMS Notification Coding
- # TAC not able to test in Developement
# SI not tested as not rolled out to Production - 10:58 Task #18 (Closed - End of life cycle): Updating Demo Pages
- 10:57 Task #32 (Closed - End of life cycle): Study CIB for Development
- 10:55 Task #33 (Closed - End of life cycle): Development
- 10:53 Task #17 (Closed - End of life cycle): Updating BRS Document
- BRS signed off, considered completed.
- 10:51 Task #113 (Closed - End of life cycle): Coding for Inserting SMS Notification Data
- 10:50 Bug #105 (Closed - End of life cycle): Create Test Script
- 10:49 Task #117 (Closed - End of life cycle): TAC & SMS Issuance Report
- 10:47 Task #119 (Closed - End of life cycle): Daily & Monthly Consolidated Transaction IB Report Modifi...
- 10:45 Task #134 (Closed - End of life cycle): Testing & Enhancement
- 10:44 Bug #157 (Work Completed-End life cycle): Validation Failed when Select the Yes radio button for ...
- 10:42 Bug #158 (Work Completed-End life cycle): Validate Local Phone Number with alphanumeric failed in...
- 10:40 Bug #159 (Work Completed-End life cycle): Validate International Phone Number with alphanumeric F...
- 10:17 Task #134: Testing & Enhancement
- # Small code changes to SMSServices.java
- 10:13 Bug #158: Validate Local Phone Number with alphanumeric failed in 3rd Party Account Transfer.
- # Fixed error in validation.xml
- 10:08 Bug #159: Validate International Phone Number with alphanumeric Failed in 3rd Party Account Trans...
- # Fixed error in validation.xml
June 25, 2010
- 13:01 Task #134: Testing & Enhancement
- # Moved logging coding to LogTables
# Minor changes to coding - 12:59 Task #119: Daily & Monthly Consolidated Transaction IB Report Modification for SMS & TAC
- # Completed coding for Daily & Monthly Consolidated Transaction IB Report
- 12:58 Task #117: TAC & SMS Issuance Report
- # Completed coding for TAC & SMS Reports
- 10:40 Bug #157: Validation Failed when Select the Yes radio button for "Send SMS to beneficiary?" In 3r...
- # Uncomment validation rule that will resolve this bug
- 10:13 Bug #159 (Closed - End of life cycle): Validate International Phone Number with alphanumeric Fail...
- Validate International Phone Number with alphanumeric Failed in 3rd Party Account Transfer.
Actual Result:
Go to ... - 10:10 Bug #158 (Closed - End of life cycle): Validate Local Phone Number with alphanumeric failed in 3r...
- Validate Local Phone Number with alphanumeric failed in 3rd Party Account Transfer.
Actual Result:
Go to "Confirm... - 10:02 Bug #157 (Closed - End of life cycle): Validation Failed when Select the Yes radio button for "Se...
- Validation Failed when Select the Yes radio button for "Send SMS to beneficiary?" In 3rd Party Transfer Account.
T...
June 21, 2010
- 16:42 Task #134: Testing & Enhancement
- # Added formatAmountValue method to SMSServices
# Changed ResultServices classes to use new method
# Added method t... - 14:54 Bug #105: Create Test Script
- New Update For Test Script...
June 18, 2010
- 17:23 Task #134: Testing & Enhancement
- # Improved SMSServices coding for better usage with SI and maintainability
# Code clean up for better readability
... - 09:16 Task #134: Testing & Enhancement
- # Improved sendSMS method implementation
# Added more columns to IB_SMS_NOTIFICATION table
# Tested all modules, re... - 09:12 Task #134 (Closed - End of life cycle): Testing & Enhancement
- Testing of SMS Notification with all modules & changes to implementation if required
- 09:08 Task #113: Coding for Inserting SMS Notification Data
- # Done, new task for enchancing SMS Notification table insert
June 17, 2010
- 19:06 Bug #105: Create Test Script
- New Update for testscript for version 3.........Continuing enhance it
June 16, 2010
- 11:56 Bug #105: Create Test Script
- new update for testscript
- 11:14 Task #82 (Development / Work In Progress): Testing SMS Notification Coding
June 15, 2010
- 18:20 Bug #105 (Development / Work In Progress): Create Test Script
- 18:17 Task #119 (Closed - End of life cycle): Daily & Monthly Consolidated Transaction IB Report Modifi...
- Add two more rows for TAC and SMS statistic
- 18:16 Task #117 (Closed - End of life cycle): TAC & SMS Issuance Report
- Create TAC & SMS Issuance Report
- 16:38 Task #113 (Closed - End of life cycle): Coding for Inserting SMS Notification Data
- Several data for SMS Notification Reports required to be saved in DB. This task is to cater for this req.uirement
- 16:32 Task #17: Updating BRS Document
- # Updated Reports section (Section 2.7)
- 11:51 Bug #105: Create Test Script
- revamp again
June 11, 2010
- 19:38 Task #17 (Development / Work In Progress): Updating BRS Document
- 19:37 Task #18 (Development / Work In Progress): Updating Demo Pages
- 18:44 Task #82: Testing SMS Notification Coding
- # Fixed small bugs with migrating SMS Notification coding to latest version in Mercurial
# Improved SMS message temp... - 14:31 Bug #105 (Closed - End of life cycle): Create Test Script
- Create test script for SMS Notification
- 14:09 Task #32 (Development / Work In Progress): Study CIB for Development
- 14:08 Task #33 (Development / Work In Progress): Development
- 14:07 Task #80 (Closed - End of life cycle): Updating BRS Document
June 09, 2010
- 10:01 Task #82: Testing SMS Notification Coding
- # Need to test GL payment and SMS sending (log to SMS Table)
June 07, 2010
- 12:15 Task #82 (Closed - End of life cycle): Testing SMS Notification Coding
- Testing and debugging of coding for SMS Notification. Performed at KFH site only.
- 12:13 Task #17: Updating BRS Document
- # Updated screenshots
# Updated content
# Changed SMS templates
- 11:59 Task #80: Updating BRS Document
- # Updated screenshots
# Updated content
# Changed SMS templates - 11:58 Task #80 (Closed - End of life cycle): Updating BRS Document
- Update SMS Notification BRS document to include changes discussed from meeting with clients on 3rd June 2010
Also available in: Atom